Exam 17: MRP and ERP
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness70 Questions
Exam 3: Forecasting139 Questions
Exam 4: Product and Service Design78 Questions
Exam 4: RELIABILITY – Static12 Questions
Exam 6: Strategic Capacity Planning for Products and Services85 Questions
Exam 7: Decision Theory– Static114 Questions
Exam 8: Process Selection and Facility Layout132 Questions
Exam 9: Work Design and Measurement129 Questions
Exam 10: learning curve– Static61 Questions
Exam 11: Location Planning and Analysis62 Questions
Exam 12: The Transportation Model– Static20 Questions
Exam 13: Management of Quality97 Questions
Exam 14: Quality Control112 Questions
Exam 15: Acceptance Sampling– Static51 Questions
Exam 16: Aggregate Planning and Master Scheduling74 Questions
Exam 17: MRP and ERP81 Questions
Exam 18: Inventory Management128 Questions
Exam 19: JIT and Lean Operations79 Questions
Exam 20: Maintenance– Static36 Questions
Exam 21: Supply Chain Management87 Questions
Exam 22: Scheduling98 Questions
Exam 23: Project Management113 Questions
Exam 24: Management of Waiting Lines64 Questions
Exam 25: Linear Programming93 Questions
Select questions type
The multiplication process used by MRP to determine lower-level requirements is called:
(Multiple Choice)
4.9/5
(44)
A net-change MRP system is one that is updated periodically but not less frequently than once a week.
(True/False)
4.8/5
(30)
Comparing known and expected capacity requirements with projected capacity availability is the job of:
(Multiple Choice)
4.8/5
(34)
Scheduled receipts differ from planned receipts in that scheduled receipts:
(Multiple Choice)
4.8/5
(38)
Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot), and quantities on hand: Deluxe Easter Basket BOM Lead Time On-Hand Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per) 2 weeks 30 Carved Chocolate Eggs ( 4 per) 1 week 50
Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs.
When should an order for carved chocolate eggs be released?
(Multiple Choice)
4.7/5
(42)
An MRP system that is updated periodically to account for all changes which have occurred within a given time interval is called a(n) ________ system.
(Multiple Choice)
4.8/5
(42)
One reason that accurate bills of material are important is that errors at one level become magnified at lower levels because of the multiplication process used by MRP.
(True/False)
4.8/5
(38)
Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot), and quantities on hand: Deluxe Easter Basket BOM Lead Time On-Hand Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per) 2 weeks 30 Carved Chocolate Eggs (4 per) 1 week 50
Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs.
What is the net requirement for dark chocolate truffles to fill this order?
(Multiple Choice)
4.9/5
(35)
One of the primary output reports of MRP concerns changes to planned orders.
(True/False)
4.8/5
(41)
Which of the following is absolutely necessary for successful implementation and operation of MRP?
(I) accurate inventory records
(II) master schedules
(III) accurate holding and backordering costs
(IV) accurate bills of materials
(Multiple Choice)
4.7/5
(34)
Lumpy demand for components results primarily from the periodic scheduling of batch production.
(True/False)
4.8/5
(36)
In MRP, EOQ models tend to be less useful for materials at the lowest levels than for upper-level assemblies of the bill of materials since higher-level assemblies have larger dollar investments.
(True/False)
5.0/5
(36)
Which one of the following is not an input in an MRP system?
(Multiple Choice)
4.8/5
(51)
Which of the following is a direct input into capacity requirements planning?
(I) the master production schedule
(II) routing information
(III) current shop loads
(IV) planned-order releases
(Multiple Choice)
4.8/5
(32)
Which of the following most closely describes dependent demand?
(Multiple Choice)
4.7/5
(41)
Which one of the following most closely describes net requirements for the current period?
(Multiple Choice)
4.8/5
(44)
_______ is choosing how many to order or make each time an order is planned.