Exam 17: MRP and ERP

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The multiplication process used by MRP to determine lower-level requirements is called:

(Multiple Choice)
4.9/5
(44)

ERP is now about enterprise applications:

(Multiple Choice)
4.9/5
(31)

A net-change MRP system is one that is updated periodically but not less frequently than once a week.

(True/False)
4.8/5
(30)

Comparing known and expected capacity requirements with projected capacity availability is the job of:

(Multiple Choice)
4.8/5
(34)

Net requirements equal gross requirements minus safety stock.

(True/False)
4.8/5
(45)

Scheduled receipts differ from planned receipts in that scheduled receipts:

(Multiple Choice)
4.8/5
(38)

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot), and quantities on hand: Deluxe Easter Basket BOM Lead Time On-Hand Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per) 2 weeks 30 Carved Chocolate Eggs ( 4 per) 1 week 50 Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. When should an order for carved chocolate eggs be released?

(Multiple Choice)
4.7/5
(42)

An MRP system that is updated periodically to account for all changes which have occurred within a given time interval is called a(n) ________ system.

(Multiple Choice)
4.8/5
(42)

One reason that accurate bills of material are important is that errors at one level become magnified at lower levels because of the multiplication process used by MRP.

(True/False)
4.8/5
(38)

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot), and quantities on hand: Deluxe Easter Basket BOM Lead Time On-Hand Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per) 2 weeks 30 Carved Chocolate Eggs (4 per) 1 week 50 Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. What is the net requirement for dark chocolate truffles to fill this order?

(Multiple Choice)
4.9/5
(35)

One of the primary output reports of MRP concerns changes to planned orders.

(True/False)
4.8/5
(41)

Which of the following is absolutely necessary for successful implementation and operation of MRP? (I) accurate inventory records (II) master schedules (III) accurate holding and backordering costs (IV) accurate bills of materials

(Multiple Choice)
4.7/5
(34)

Lumpy demand for components results primarily from the periodic scheduling of batch production.

(True/False)
4.8/5
(36)

In MRP, EOQ models tend to be less useful for materials at the lowest levels than for upper-level assemblies of the bill of materials since higher-level assemblies have larger dollar investments.

(True/False)
5.0/5
(36)

Which one of the following is not an input in an MRP system?

(Multiple Choice)
4.8/5
(51)

Which statement concerning MRP II is false?

(Multiple Choice)
4.9/5
(48)

Which of the following is a direct input into capacity requirements planning? (I) the master production schedule (II) routing information (III) current shop loads (IV) planned-order releases

(Multiple Choice)
4.8/5
(32)

Which of the following most closely describes dependent demand?

(Multiple Choice)
4.7/5
(41)

Which one of the following most closely describes net requirements for the current period?

(Multiple Choice)
4.8/5
(44)

_______ is choosing how many to order or make each time an order is planned.

(Multiple Choice)
4.9/5
(44)
Showing 21 - 40 of 81
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)