Exam 23: Project Management
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness70 Questions
Exam 3: Forecasting139 Questions
Exam 4: Product and Service Design78 Questions
Exam 4: RELIABILITY – Static12 Questions
Exam 6: Strategic Capacity Planning for Products and Services85 Questions
Exam 7: Decision Theory– Static114 Questions
Exam 8: Process Selection and Facility Layout132 Questions
Exam 9: Work Design and Measurement129 Questions
Exam 10: learning curve– Static61 Questions
Exam 11: Location Planning and Analysis62 Questions
Exam 12: The Transportation Model– Static20 Questions
Exam 13: Management of Quality97 Questions
Exam 14: Quality Control112 Questions
Exam 15: Acceptance Sampling– Static51 Questions
Exam 16: Aggregate Planning and Master Scheduling74 Questions
Exam 17: MRP and ERP81 Questions
Exam 18: Inventory Management128 Questions
Exam 19: JIT and Lean Operations79 Questions
Exam 20: Maintenance– Static36 Questions
Exam 21: Supply Chain Management87 Questions
Exam 22: Scheduling98 Questions
Exam 23: Project Management113 Questions
Exam 24: Management of Waiting Lines64 Questions
Exam 25: Linear Programming93 Questions
Select questions type
The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.
Free
(True/False)
4.8/5
(40)
Correct Answer:
True
A project is represented by the following diagram:
The critical path for the network shown is:

Free
(Multiple Choice)
4.8/5
(29)
Correct Answer:
D
If an activity is determined to be on the critical path, that means that unlike activities that are not on the critical path, it will affect project:
Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
E
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.7/5
(32)
Consider the following work breakdown structure:
What is the estimated slack time for activity E?

(Multiple Choice)
4.7/5
(31)
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
(True/False)
4.8/5
(31)
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(39)
Consider the following work breakdown structure:
What is the probability that the critical path for this project will be completed within 200 days?

(Multiple Choice)
4.8/5
(30)
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity Y?

(Multiple Choice)
4.8/5
(34)
In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.
(True/False)
4.9/5
(37)
A method used for establishing a logical framework for identifying the required activities for the project is called:
(Multiple Choice)
4.8/5
(26)
Consider the following work breakdown structure:
What is the estimated expected (mean) time for project completion?

(Multiple Choice)
4.8/5
(27)
The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.
(True/False)
4.8/5
(29)
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(36)
Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is:
(Multiple Choice)
4.8/5
(28)
Which of the following are limitations of PERT and CPM?
(I) Time estimates may include a fudge factor.
(II) Important activities may be overlooked.
(III) It is an after-the-fact analysis.
(Multiple Choice)
4.8/5
(42)
In a project network, the critical path is the sequence of activities which has the:
(Multiple Choice)
4.7/5
(35)
The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.
(True/False)
4.7/5
(43)
Activities not on the critical path have a slack time equal to zero.
(True/False)
4.8/5
(38)
Showing 1 - 20 of 113
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)