The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.

Free
(True/False)
4.8/5
(40)
Correct Answer:
Verified

True

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: The critical path for the network shown is:

Free
(Multiple Choice)
4.8/5
(29)
Correct Answer:
Verified

D

If an activity is determined to be on the critical path, that means that unlike activities that are not on the critical path, it will affect project:

Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
Verified

E

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity Z? What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.7/5
(32)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity E? What is the estimated slack time for activity E?

(Multiple Choice)
4.7/5
(31)

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

(True/False)
4.8/5
(31)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(39)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 200 days? What is the probability that the critical path for this project will be completed within 200 days?

(Multiple Choice)
4.8/5
(30)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity Y? What is the estimated expected (mean) time for activity Y?

(Multiple Choice)
4.8/5
(34)

In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.

(True/False)
4.9/5
(37)

A method used for establishing a logical framework for identifying the required activities for the project is called:

(Multiple Choice)
4.8/5
(26)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for project completion? What is the estimated expected (mean) time for project completion?

(Multiple Choice)
4.8/5
(27)

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.

(True/False)
4.8/5
(29)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(36)

Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is:

(Multiple Choice)
4.8/5
(28)

Which of the following are limitations of PERT and CPM? (I) Time estimates may include a fudge factor. (II) Important activities may be overlooked. (III) It is an after-the-fact analysis.

(Multiple Choice)
4.8/5
(42)

In a project network, the critical path is the sequence of activities which has the:

(Multiple Choice)
4.7/5
(35)

Gantt charts are most closely associated with

(Multiple Choice)
4.8/5
(42)

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.

(True/False)
4.7/5
(43)

Activities not on the critical path have a slack time equal to zero.

(True/False)
4.8/5
(38)