Exam 5: Project Planning: Scope and the Work Breakdown Structure
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
The scope boundary establishes only those elements that are a part of the project work to be completed by the project team.
(True/False)
4.9/5
(28)
All of the following are included in the Project Scope except:
(Multiple Choice)
4.8/5
(34)
What is the Delphi technique? When would it be an appropriate estimating technique for an IT project?
(Essay)
4.8/5
(45)
Project scope is a statement detailing the features and functions that must support the IT solution.
(True/False)
4.9/5
(30)
Why is it important to define the project's scope accurately and completely?
(Essay)
5.0/5
(35)
Which of the following processes of Scope Management Process centers on defining and documenting the stakeholders' needs to properly manage expectations?
(Multiple Choice)
4.9/5
(29)
A work breakdown structure (WBS) represents a logical decomposition of the work to be performed and how the product, service, or result is naturally subdivided.
(True/False)
4.9/5
(31)
What are some of the advantages and disadvantages of a project team working together to develop the project plan?
(Essay)
4.8/5
(31)
Which of the following processes of Scope Management Process ensuring that controls are in place to manage proposed scope changes once the project's scope is accepted?
(Multiple Choice)
4.8/5
(27)
One way to communicate the project's deliverables is to create a deliverable structure chart.
(True/False)
4.8/5
(35)
An estimation technique characterized by picking numbers out of the air or "ballparking".
(Multiple Choice)
4.9/5
(32)
_____ can be a very effective estimating technique by forcing examination of project risks so that specific budget or schedule targets can be achieved.
(Multiple Choice)
4.9/5
(37)
What is increasing featurism and what are the impacts it has on a project?
(Essay)
4.9/5
(38)
The scope statement documents the sponsor's needs and expectations.
(True/False)
4.8/5
(31)