Exam 5: Project Planning: Scope and the Work Breakdown Structure
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
Basing an estimate of activity durations on experience gained from working on similar projects is called analogous estimation.
Free
(True/False)
4.9/5
(40)
Correct Answer:
True
An estimation technique characterized by the recruitment of multiple experts who provide rounds of estimates until a consensus estimate emerges.
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
B
Describe bottom-up estimating.What are some advantages and disadvantages of bottom-up estimating?
Free
(Essay)
4.8/5
(28)
Correct Answer:
Bottom-up estimating involves dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours, person-weeks, or person-months for each module. The project manager, or better yet the project team, can provide reasonable time estimates for each activity. Bottom-up estimated is straightforward; however, confusing effort with progress can be problematic. When doing bottom-up estimating often analogous estimating is employed. If the analogy is not well chosen or unanticipated differences emerge, the estimation error will likely be compounded.
Describe the estimation technique called Guesstimating.What are the strengths and weaknesses of this approach?
(Essay)
4.8/5
(39)
In much the same fashion as the claim "you can never be too rich", when developing a WBS, one can never have too much detail in planning activities.
(True/False)
4.8/5
(29)
An estimation technique characterized by the dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours, person-weeks, or person-months for each module best describes
(Multiple Choice)
4.9/5
(34)
In developing a scope change request form, what elements should be included and why?
(Essay)
4.8/5
(30)
Which of the following processes of Scope Management Process decomposes or divides the major project deliverables into smaller and more manageable components?
(Multiple Choice)
4.9/5
(27)
The _____ estimation method usually costs more and takes longer than other methods.
(Multiple Choice)
4.8/5
(32)
Identify and briefly describe, the five processes that support project scope management.
(Essay)
4.9/5
(39)
The significant event at the conclusion of each phase is called _____.
(Multiple Choice)
4.9/5
(41)
According to the text, most real-world estimating is made using top-down estimating.
(True/False)
4.8/5
(37)
Describe top-down estimating.What are some advantages and disadvantages of top-down estimating?
(Essay)
4.7/5
(37)
The text describes three project problems with metaphorical names that scope change control is concerned with.Name and describe these problems and then illustrate how scope change control can ameliorate or remedy the problem.
(Essay)
4.7/5
(40)
With _____, activity estimates are usually provided by the team members.
(Multiple Choice)
4.8/5
(33)
The _____ helps to identify the main functions or features of the system and the different users or external systems that interact with the system.
(Multiple Choice)
4.8/5
(36)
_____ is the most common, real-world method of estimating projects.
(Multiple Choice)
4.9/5
(32)
Showing 1 - 20 of 94
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)