Exam 5: Project Planning: Scope and the Work Breakdown Structure
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
The work breakdown structure (WBS) decomposes, or subdivides, the project into smaller components and more manageable units of work called work packages.
(True/False)
4.8/5
(32)
The development of a work breakdown structure is an interim step to define detailed work packages used to estimate the project schedule and budget.
(True/False)
4.9/5
(42)
A significant event or achievement that provides evidence that a deliverable is complete is called a _____
(Multiple Choice)
4.8/5
(27)
What is the purpose of a scope statement? Give an example of a scope statement that might address the needs of an organization which is looking to establish their first Internet web site.
(Short Answer)
4.9/5
(32)
An estimation technique characterized by schedule and cost estimates of how long something should take or should cost.
(Multiple Choice)
4.8/5
(34)
Since adding features to a project will likely have a negative impact on schedules and budgets, once the project's scope has been defined, no new features should added.
(True/False)
4.8/5
(34)
According to the PMBOK area of scope management, one of the processes is scope planning which means ensuring that authority and resources are committed to developing a scope management plan.
(True/False)
4.8/5
(35)
Scope change control is concerned with ensuring that any changes to the project scope will be beneficial, with determining that an actual scope change has occurred, and with managing the actual changes when and as they occur.
(True/False)
4.7/5
(39)
Which of the following processes of Scope Management Process provides confirmation and formal acceptance that the project's scope is accurate, complete, and supports the project's goal?
(Multiple Choice)
4.9/5
(37)
This estimation technique may be driven by an upper management mandate.
(Multiple Choice)
4.9/5
(28)
Compare and contrast top-down and bottom-up estimating? Why would you choose one method over the other?
(Essay)
4.8/5
(43)
The Delphi technique is a quick and economical way to estimate the duration and costs of project activities.
(True/False)
4.9/5
(34)
Showing 61 - 80 of 94