Exam 9: Managing Project Quality
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
The CMM/CMMI level which is the first to introduce technology change management _________ ?
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
E
________ provides the basis for continuous improvement by auditing and evaluating the results from quality control measurements so that appropriate quality standards and operational definitions are used.
Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
B
Which of the following is a product-oriented activity that attempts to determine if the system or project deliverable meets the customer or client's expectations?
Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
B
Defect arrival rates, Defects by phase, and Fix Response time are all process metrics.
(True/False)
4.8/5
(35)
Taken together, the concepts of quality management, verification and validation, and quality control support the overall project quality management plan.
(True/False)
4.7/5
(35)
The CMM/CMMI level which is the first to introduce key process areas is _________ ?
(Multiple Choice)
4.9/5
(39)
_________ introduced the control chart to better understand process variations.
(Multiple Choice)
5.0/5
(33)
What is scientific management? Why was it so popular? Why was it so controversial?
(Essay)
4.8/5
(40)
________ is monitoring and documenting the results of executing project quality activities to eliminate causes of unsatisfactory performance and implement new processes and techniques to improve project quality throughout the organization.
(Multiple Choice)
4.7/5
(37)
The core values of quality programs proposed by Shewhart, Deming, Juran, Ishikawa, and Crosby include:
(Multiple Choice)
4.9/5
(37)
What is a Pareto diagram? How can it be used as a quality control tool for an IT project?
(Essay)
4.8/5
(34)
The CMM/CMMI level which documents and standardizes software engineering and management processes throughout the organization is _________ ?
(Multiple Choice)
4.9/5
(33)
In general control limits are set at + or - ________ standard deviations which provides ________ probability limits.
(Multiple Choice)
4.8/5
(37)
The CMM/CMMI level which is characterized by the addition of Software Quality management and Quantitative Process Management is _________ ?
(Multiple Choice)
4.8/5
(26)
A process that is shown to have eight successive values that are more than two standard deviations away from the mean might be correctly categorized as stable or in statistical control.
(True/False)
4.8/5
(36)
Verification activities focus on asking the question of whether we followed the right procedures and processes.
(True/False)
4.9/5
(39)
What is a control chart? When is a process said to be in statistical control? How would you know if it was not?
(Essay)
4.7/5
(32)
Showing 1 - 20 of 60