Exam 18: Project Management for New Products and Processes
Exam 1: Product Line Planning and the Systems Approach114 Questions
Exam 2: Productivity and Strategic Planning115 Questions
Exam 3: Demand Creation and Predictive Planning114 Questions
Exam 4: Understanding Quality: ITS Management and Strategic Importance114 Questions
Exam 5: Process Configuration Strategies111 Questions
Exam 6: Process Analysis and Redesign115 Questions
Exam 7: Quality Assurance115 Questions
Exam 8: Management of Technology Mot101 Questions
Exam 9: Teamwork Planning Requires Job Design113 Questions
Exam 10: Supply Chain Capacity Planning113 Questions
Exam 11: Facilities Planning: Location and Layout112 Questions
Exam 12: Materials Management Impacts All Supply Chain Participants110 Questions
Exam 13: Aggregate Planning to Balance Supply and Demand106 Questions
Exam 14: Inventory Management for Smooth and Continuous Demand Patterns114 Questions
Exam 15: Material Requirements Planning Mrp for Sporadic Demand Patterns116 Questions
Exam 16: Production Scheduling for Manufacturing and Service Operations116 Questions
Exam 17: Cycle-Time Management Increases Productivity117 Questions
Exam 18: Project Management for New Products and Processes110 Questions
Exam 19: Change Management With Faster Project Completions103 Questions
Exam 20: Sustainability Issues: Environment, Ethics, and Security111 Questions
Select questions type
Projects that are tracked by good information systems require more management time to produce controlled innovative success stories.
(True/False)
4.8/5
(38)
Which of the following stages is NOT part of designing new products?
(Multiple Choice)
4.9/5
(45)
The fundamental idea of resource leveling is to switch extra resources from places where they are not essential to places where they could be used immediately.
(True/False)
4.9/5
(36)
Which of the following are considered to be part of the five project life-cycle stages?
(Multiple Choice)
4.8/5
(41)
Knowledge management of complex systems is usually satisfied by explicit information alone.
(True/False)
4.7/5
(30)
Engineering change orders often appear to be major alterations in the product design but turn out to be minor instead.
(True/False)
4.8/5
(44)
If specific technical,technological,and production skill information can be transfered by written documents to company vendors,then they qualify as instances of explicit knowledge.
(True/False)
4.8/5
(34)
When the variance of a noncritical project path is larger than the variance along the critical path,it is possible that the noncritical path will become critical.
(True/False)
4.9/5
(37)
Slack (associated with an activity) describes the amount of time that can be treated as a safety buffer for slippage.
(True/False)
4.7/5
(37)
A Gantt project-planning chart is good for any project except those where visualizing the basic structure of the system is required.
(True/False)
4.7/5
(38)
H & W construction have been awarded a job to replace the vinyl and carpet throughout Mr.Bruce's house.The team has prepared the following estimates.Below are the activities and times for installing a laminate floor.
Construct the appropriate network diagram and label the ES,EF,LS,and LF times.Alternatively,create the table of ES,EF,LS,and LF.What is the critical path? How many hours are in the critical path? Mrs.Bruce needs this time estimate to plan an upcoming party.Mrs.Bruce is hosting a house and garden party for her daughter,Daisy,and is anxious for the team to complete the project.H & W Construction will be paid an extra $15 per hour for early completion (any time less than the critical path).Tasks B,I,and J can be shortened.B by 2 hours;I and J by 5 hours;each reduction will cost $12 per hour.Which if any of the three tasks will you shorten?

(Essay)
4.8/5
(47)
_____enables the critical path to be identified and permits the determination of slack.
(Multiple Choice)
4.8/5
(41)
_____ is when each activity will be done in the least possible or minimum time.
(Multiple Choice)
4.7/5
(44)
When activities are represented as arrows,then the node circles are called:
(Multiple Choice)
4.8/5
(32)
Normal time is associated with the minimum necessary spending on project activities because there is no great stress on completing the project as soon as possible.
(True/False)
4.8/5
(42)
Showing 21 - 40 of 110