Exam 3: The Project Management Process Groups
Which planning process is associated with project scope management?
A
What process group does the project integration management knowledge area map to through the activities of developing project charters?
A
List and describe the five process management groups.
Initiating processes include defining and authorizing a project or project phase. Initiating processes take place during each phase of a project. Therefore, you cannot equate process groups with project phases. Recall that there can be different project phases, but all projects will include all five process groups. For example, project managers and teams should reexamine the business need for the project during every phase of the project life cycle to determine if the project is worth continuing. Initiating processes are also required to end a project. Someone must initiate activities to ensure that the project team completes all the work, documents lessons learned, assigns project resources, and that the customer accepts the work.
Planning processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs. There are several plans for projects, such as the scope management plan, schedule management plan, cost management plan, procurement management plan, and so on, defining each knowledge area as it relates to the project at that point in time. For example, a project team must develop a plan to define the work that needs to be done for the project, to schedule activities related to that work, to estimate costs for performing the work, to decide what resources to procure to accomplish the work, and so on. To account for changing conditions on the project and in the organization, project teams often revise plans during each phase of the project life cycle.
Executing processes include coordinating people and other resources to carry out the various plans and produce the products, services, or results of the project or phase. Examples of executing processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.
Monitoring and controlling processes include regularly measuring and monitoring progress to ensure that the project team meets the project objectives. The project manager and staff monitor and measure progress against the plans and take corrective action when necessary. A common monitoring and controlling process is reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track.
Closing processes include formalizing acceptance of the project or project phase and ending it efficiently. Administrative activities are often involved in this process group, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project.
A(n) _____ is a meeting held at the beginning of a project so that stakeholders can meet each other, review the goals of the project, and discuss future plans.
A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.
What process provides enterprise environmental factors as an output?
A(n) _____ is the person responsible for the business value of the project and for deciding what work to do and in what order when using a Scrum method.
The project stakeholder management knowledge area maps to which process group by identifying stakeholders?
Monitoring and controlling processes overlap all of the other project management process groups.
_____ is a project management methodology that defines 45 separate subprocesses and organizes these into eight process groups.
Which planning process is within the Project Scope Management knowledge area?
_____ are short descriptions written by customers of what they need a Scrum system to do for them.
The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
The level of activity and length of each process group varies for every project.
Project initiation involves taking the actions necessary to ensure that activities in the project plan are completed.
_____ progress from initiation activities to planning activities, executing activities, monitoring and controlling activities, and closing activities.
_________ issues often occur during project execution, especially conflicts.
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)