Exam 6: Project Schedule Management
Exam 1: Introduction to Project Management91 Questions
Exam 2: The Project Management Information Technology Context85 Questions
Exam 3: The Project Management Process Groups83 Questions
Exam 4: Project Integration Management83 Questions
Exam 5: Project Scope Management77 Questions
Exam 6: Project Schedule Management99 Questions
Exam 7: Project Cost Management98 Questions
Exam 8: Project Quality Management81 Questions
Exam 9: Project Resource Management85 Questions
Exam 10: Project Communications Management73 Questions
Exam 11: Project Risk Management79 Questions
Exam 12: Project Procurement Management82 Questions
Exam 13: Project Stakeholder Management50 Questions
Select questions type
In project schedule management, the process of _____ involves deciding how many people, equipment, and materials a project team should use to perform project activities.
Free
(Short Answer)
4.8/5
(39)
Correct Answer:
estimating activity resources
Which dependencies involve relationships between project and non-project activities?
Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
C
An activity is an element of work that has an expected duration, cost, and resource requirements.
Free
(True/False)
4.9/5
(24)
Correct Answer:
True
What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?
(Multiple Choice)
4.7/5
(37)
The _____ is based on the fact that any complex system at any point in time often has only one aspect or constraint that limits its ability to achieve more of its goal.
(Short Answer)
4.9/5
(24)
Which provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format?
(Multiple Choice)
4.9/5
(19)
The main outputs of _____ include work performance information, schedule forecasts, change requests, project management plan updates, and project documents updates.
(Short Answer)
4.7/5
(31)
What is the first process involved in project schedule management?
(Multiple Choice)
4.8/5
(37)
How does critical chain scheduling protect tasks on the critical chain from being delayed?
(Multiple Choice)
4.8/5
(43)
A(n) _____ Gantt chart compares planned and actual project schedule information.
(Short Answer)
4.9/5
(34)
Describe critical path analysis. How is the critical path calculated?
(Essay)
4.8/5
(23)
In project schedule management, which is an output of controlling the schedule?
(Multiple Choice)
4.8/5
(34)
Which technique involves doing activities in parallel that one would normally do in sequence?
(Multiple Choice)
4.8/5
(38)
A backward pass through the network diagram determines the early start and early finish dates for each activity.
(True/False)
4.8/5
(29)
_____ occurs when a resource works on more than one task at a time.
(Short Answer)
5.0/5
(38)
In project schedule management, which process involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?
(Multiple Choice)
4.8/5
(32)
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
(True/False)
4.9/5
(38)
In a Gantt chart, thick black bars represent milestones achieved in a project.
(True/False)
4.8/5
(37)
In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?
(Multiple Choice)
5.0/5
(31)
In an AOA network diagram, what occurs when two or more activities follow a single node?
(Multiple Choice)
4.9/5
(34)
Showing 1 - 20 of 99
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)