Exam 4: Project Integration Management
Exam 1: Introduction to Project Management91 Questions
Exam 2: The Project Management Information Technology Context85 Questions
Exam 3: The Project Management Process Groups83 Questions
Exam 4: Project Integration Management83 Questions
Exam 5: Project Scope Management77 Questions
Exam 6: Project Schedule Management99 Questions
Exam 7: Project Cost Management98 Questions
Exam 8: Project Quality Management81 Questions
Exam 9: Project Resource Management85 Questions
Exam 10: Project Communications Management73 Questions
Exam 11: Project Risk Management79 Questions
Exam 12: Project Procurement Management82 Questions
Exam 13: Project Stakeholder Management50 Questions
Select questions type
The _____ is the discount rate that results in an NPV of zero for a project.
Free
(Short Answer)
4.9/5
(36)
Correct Answer:
internal rate of return
internal rate of return (IRR)
IRR
Information systems can help an organization support a strategy of being a low-cost producer.
Free
(True/False)
4.7/5
(30)
Correct Answer:
True
The organization should complete low-priority projects before high-priority ones, if the low-priority ones take less time.
Free
(True/False)
4.9/5
(35)
Correct Answer:
False
_____ involves identifying and managing the points of interaction between various elements of the project.
(Short Answer)
4.7/5
(41)
Which document recognizes the existence of a project and provides direction on the project's objectives and management?
(Multiple Choice)
4.9/5
(37)
_____ refer to undesirable situations that prevent an organization from achieving its goals.
(Short Answer)
4.8/5
(42)
Interface management involves identifying and managing the points of interaction between various elements of a project.
(True/False)
4.8/5
(30)
In a weighted scoring model, what percent must the sum of the weights of all the criteria total?
(Multiple Choice)
4.8/5
(37)
Which process involves working with stakeholders to create the document that formally authorizes a project?
(Multiple Choice)
4.9/5
(34)
Many projects fail because of unclear requirements and expectations, so starting with a payback analysis makes a lot of sense.
(True/False)
5.0/5
(31)
Which section of the project management plan includes external interfaces, internal structure, as well as roles and responsibilities?
(Multiple Choice)
4.7/5
(29)
A _____ is a starting point, a measurement, or an observation that is documented so that it can be used for future comparison. changes.
(Short Answer)
4.9/5
(39)
What type of analysis involves calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time?
(Multiple Choice)
4.8/5
(40)
An organization should consider only projects with a negative NPV if financial value is a key criterion for project selection.
(True/False)
4.8/5
(36)
Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an organization's business.
(True/False)
4.9/5
(32)
Showing 1 - 20 of 83
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)