 Which approach for constructing a WBS uses a similar project's WBS as a starting point?

(Multiple Choice)
4.9/5
(37)

 _____ includes the processes involved in defining and controlling what work is or is not included in a project.

(Short Answer)
5.0/5
(26)

 List and briefly describe the six main processes involved in project scope management.

(Essay)
4.9/5
(29)

 Scope creep if not managed well can lead to the failure of information technology projects.

(True/False)
4.8/5
(37)

 The project management plan, project documents, enterprise environmental factors, and organizational process assets are the primary inputs for creating a WBS.

(True/False)
4.9/5
(33)

 Deliverables are only product-related, such as a piece of hardware or software.

(True/False)
4.8/5
(30)

 The executing tasks of the WBS remain constant from project to project.

(True/False)
4.7/5
(36)

 The main outputs of scope definition are the _____ and project document updates.

(Short Answer)
4.8/5
(38)

 The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.

(True/False)
4.9/5
(37)

 The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.

(True/False)
4.9/5
(45)

 What are some of the suggestions for improving the requirements process?

(Essay)
4.9/5
(34)

 Which document should list and describe all of the deliverables required for the project?

(Multiple Choice)
4.8/5
(45)

 A unit of work should appear at only one place in the WBS.

(True/False)
4.9/5
(38)

 The project's size, complexity, importance, and other factors do not affect how much effort is spent on collecting requirements for scope planning.

(True/False)
4.9/5
(37)

 Which statement best describes scope?

(Multiple Choice)
4.7/5
(39)

 Subdividing the project deliverables into smaller pieces is known as _____.

(Short Answer)
4.7/5
(42)

 The tasks in a WBS must be developed as a sequential list of steps.

(True/False)
4.8/5
(33)

 Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?

(Multiple Choice)
4.7/5
(46)

 Project scope statements must include the project boundaries, constraints, and assumptions.

(True/False)
4.7/5
(33)

 A hierarchy is used to show the levels of _____ in the WBS.

(Short Answer)
4.9/5
(32)