Exam 8: Scheduling Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.

(True/False)
5.0/5
(31)

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - Plan Research?​  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity A - "Plan Research"?​ 

(Multiple Choice)
4.9/5
(27)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project?  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project? 

(Multiple Choice)
4.7/5
(41)

Which of these represents a typical problem that can make it difficult to estimate activity durations accurately?​ 

(Multiple Choice)
4.8/5
(38)

Despite the insights that PERT provides,there are still practical limitations that impact its usefulness.All of the following difficulties are associated with the use of PERT EXCEPT: 

(Multiple Choice)
4.9/5
(33)

To use the enumeration method of determining the critical path,we list or enumerate all of the paths through the network.

(True/False)
4.7/5
(31)

The primary advantage of PERT is that it removes uncertainty from the estimates of activity durations,thereby increasing confidence in the reliability of a project schedule.

(True/False)
4.8/5
(41)

If the project manager changes an activity on the critical path to start at a later date,then the whole project will end at a later date.

(True/False)
4.9/5
(34)

The critical path is the sequence of schedule activities determining the duration of the project,and is generally the shortest path through the project.

(True/False)
4.8/5
(35)

Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.

(True/False)
4.7/5
(32)

The "start-to-start" logical relationship used in activity sequencing applies to the case in which a successor activity cannot start until a predecessor activity has started.

(True/False)
4.8/5
(39)

PERT refers to Program Evaluation and Review Technique,which was developed in the 1950s to better understand how variability in the individual activity durations impacts the entire project schedule.

(True/False)
4.8/5
(29)

Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?​ 

(Multiple Choice)
4.7/5
(29)

  Figure 7-1 Assembly Project -Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - Attach Modules 1 & 2?​  Figure 7-1 Assembly Project -Consider the Assembly Project depicted in Figure 7-1.Based on the information provided,what is the early start date for activity D - "Attach Modules 1 & 2"?​ 

(Multiple Choice)
5.0/5
(39)

This term is defined as the total number of work periods (not including holidays or other non-work periods)required to complete a schedule activity,usually expressed as workdays or workweeks:​ 

(Multiple Choice)
4.9/5
(32)

Describe free float and how you can use it to your advantage in scheduling and managing a project.

(Essay)
4.8/5
(35)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date? 

(Multiple Choice)
4.9/5
(25)

Milestones are important points in a project schedule that can serve as check points for project managers and sponsors.Which of the following could be a reason to identify a milestone during project schedule planning?​ 

(Multiple Choice)
4.8/5
(33)

The first process in developing a project schedule is to identify all the resources available to work on the project.

(True/False)
4.7/5
(29)

  Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network?  Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network? 

(Multiple Choice)
4.7/5
(31)
Showing 21 - 40 of 56
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)