Exam 8: Scheduling Projects
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Chartering Projects39 Questions
Exam 4: Organizational Capability: Structure, Culture and Roles50 Questions
Exam 5: Leading and Managing Project Teams46 Questions
Exam 6: Stakeholder Analysis and Communication Planning46 Questions
Exam 7: Scope Planning44 Questions
Exam 8: Scheduling Projects56 Questions
Exam 9: Resourcing Projects45 Questions
Exam 10: Budgeting Projects46 Questions
Exam 11: Project Risk Planning45 Questions
Exam 12: Project Quality Planning and Project Kick-Off45 Questions
Exam 13: Project Supply Chain Management45 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project and Realizing the Benefits30 Questions
Select questions type
Which of these is NOT one of the items that can provide useful assistance to a project team to define the activities of a project?
(Multiple Choice)
4.9/5
(31)
Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?

(Multiple Choice)
4.8/5
(36)
Figure 7-2 Research Project
-Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?

(Multiple Choice)
4.8/5
(37)
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?

(Multiple Choice)
4.7/5
(32)
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?

(Multiple Choice)
4.7/5
(33)
Even small delays on "near-critical" activities can change the critical path of a project.
(True/False)
5.0/5
(33)
A successor activity is the schedule activity that follows a predecessor activity,as determined by their logical relationship.
(True/False)
4.7/5
(36)
The length of time to perform an activity is often dependent upon who will do that work.
(True/False)
4.9/5
(36)
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?

(Multiple Choice)
4.8/5
(35)
Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?

(Multiple Choice)
4.8/5
(28)
When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.
(True/False)
4.8/5
(38)
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:
(Multiple Choice)
4.9/5
(35)
Which of the following responses identifies a common type of logical dependency used to sequence project activities?
(Multiple Choice)
4.9/5
(38)
While the lowest level of decomposition in a WBS is the work package,work packages can still be decomposed further into work activities.
(True/False)
4.8/5
(33)
Faced with significant schedule challenges,the project manager has an ethical responsibility to do all of the following EXCEPT:
(Multiple Choice)
4.9/5
(35)
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?

(Multiple Choice)
4.9/5
(32)