Exam 8: Scheduling Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of these is NOT one of the items that can provide useful assistance to a project team to define the activities of a project?​ 

(Multiple Choice)
4.9/5
(31)

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?​  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?​ 

(Multiple Choice)
4.8/5
(36)

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - Review Reports?​  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2.Based on the information provided,what is the late start date for activity C - "Review Reports"?​ 

(Multiple Choice)
4.8/5
(37)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project? 

(Multiple Choice)
4.7/5
(32)

  Figure 7-6 Network Scheduling Data -Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?  Figure 7-6 Network Scheduling Data -Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F? 

(Multiple Choice)
4.7/5
(33)

Even small delays on "near-critical" activities can change the critical path of a project.

(True/False)
5.0/5
(33)

A successor activity is the schedule activity that follows a predecessor activity,as determined by their logical relationship.

(True/False)
4.7/5
(36)

The length of time to perform an activity is often dependent upon who will do that work.

(True/False)
4.9/5
(36)

  Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project?  Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6.What is the expected duration of this project? 

(Multiple Choice)
4.8/5
(35)

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date? 

(Multiple Choice)
4.8/5
(28)

When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.

(True/False)
4.8/5
(38)

Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:​ 

(Multiple Choice)
4.9/5
(35)

Which of the following responses identifies a common type of logical dependency used to sequence project activities?​ 

(Multiple Choice)
4.9/5
(38)

While the lowest level of decomposition in a WBS is the work package,work packages can still be decomposed further into work activities.

(True/False)
4.8/5
(33)

Faced with significant schedule challenges,the project manager has an ethical responsibility to do all of the following EXCEPT:​ 

(Multiple Choice)
4.9/5
(35)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date? 

(Multiple Choice)
4.9/5
(32)
Showing 41 - 56 of 56