Exam 5: Projects Manufacturing and Service Processes
Exam 1: Operations and Supply Chain Management71 Questions
Exam 2: Strategy and Sustainability48 Questions
Exam 3: Forecasting90 Questions
Exam 4: Strategic Capacity Management55 Questions
Exam 4: PART-A: Learning Curves49 Questions
Exam 5: Projects Manufacturing and Service Processes72 Questions
Exam 6: Manufacturing Processes56 Questions
Exam 6: PART-A: Break-Even Analysis9 Questions
Exam 7: Service Processes76 Questions
Exam 8: Sales and Operations Planning58 Questions
Exam 9: Material Requirements Planning81 Questions
Exam 10: Quality Management and Six-Sigma Supply Chain Processes and Analytics129 Questions
Exam 11: Inventory Management100 Questions
Exam 12: Lean Supply Chains71 Questions
Exam 13: Global Sourcing and Procurement64 Questions
Exam 14: Location, Logistics and Distribution54 Questions
Select questions type
The critical path in a CPM analysis is always the shortest path through the network.
Free
(True/False)
4.8/5
(39)
Correct Answer:
False
Which of the following is a graphic project report used in project management?
Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
E
Earned Value Management (EVM)is a technique for measuring project progress in an objective manner.
Free
(True/False)
4.8/5
(40)
Correct Answer:
True
Using the Time-Cost CPM model,the crash time is the shortest possible time allowed for each activity in the project.
(True/False)
4.9/5
(44)
series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?
(Multiple Choice)
4.7/5
(32)
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?
(Multiple Choice)
4.8/5
(40)
The project indirect costs associated with a project include overhead,facilities,and resource opportunity costs.
(True/False)
4.9/5
(40)
matrix project attempts to blend properties of functional and pure project structures.
(True/False)
4.7/5
(38)
A work breakdown structure is used in project management but it is not used when the critical path method is involved.
(True/False)
4.8/5
(34)
You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?
(Multiple Choice)
4.9/5
(33)
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.
(True/False)
4.8/5
(48)
In CPM the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.
(True/False)
4.9/5
(35)
In the Time-Cost CPM model,cost is assumed to be a linear function of time.
(True/False)
4.8/5
(38)
Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?


(Multiple Choice)
4.7/5
(39)
The critical path in a CPM analysis is found by locating the activities times with zero slack.
(True/False)
4.9/5
(32)
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs)?


(Multiple Choice)
4.9/5
(35)
simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
Using the CPM,which activities have slack in this project?

(Multiple Choice)
4.7/5
(33)
PERT is an abbreviation for which of the following methodologies?
(Multiple Choice)
4.8/5
(32)
Earned Value Management (EVM)has the capability to combine measurements of scope,schedule,and cost in a project.
(True/False)
4.8/5
(31)
Showing 1 - 20 of 72
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)