The critical path in a CPM analysis is always the shortest path through the network.

Free
(True/False)
4.8/5
(39)
Correct Answer:
Verified

False

Which of the following is a graphic project report used in project management?

Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
Verified

E

Earned Value Management (EVM)is a technique for measuring project progress in an objective manner.

Free
(True/False)
4.8/5
(40)
Correct Answer:
Verified

True

Using the Time-Cost CPM model,the crash time is the shortest possible time allowed for each activity in the project.

(True/False)
4.9/5
(44)

series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?

(Multiple Choice)
4.7/5
(32)

You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?

(Multiple Choice)
4.8/5
(40)

The project indirect costs associated with a project include overhead,facilities,and resource opportunity costs.

(True/False)
4.9/5
(40)

matrix project attempts to blend properties of functional and pure project structures.

(True/False)
4.7/5
(38)

A work breakdown structure is used in project management but it is not used when the critical path method is involved.

(True/False)
4.8/5
(34)

You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?

(Multiple Choice)
4.9/5
(33)

A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.

(True/False)
4.8/5
(48)

In CPM the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.

(True/False)
4.9/5
(35)

In the Time-Cost CPM model,cost is assumed to be a linear function of time.

(True/False)
4.8/5
(38)

Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days,what is the total time of the project and total cost? Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?

(Multiple Choice)
4.7/5
(39)

The critical path in a CPM analysis is found by locating the activities times with zero slack.

(True/False)
4.9/5
(32)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs)? You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project direct costs are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs)?

(Multiple Choice)
4.9/5
(35)

simple project listing of five activities,their predecessors,and their respective time estimates are presented below: simple project listing of five activities,their predecessors,and their respective time estimates are presented below:   Using the CPM,which activities have slack in this project? Using the CPM,which activities have slack in this project?

(Multiple Choice)
4.7/5
(33)

What is a work breakdown structure?

(Multiple Choice)
4.9/5
(34)

PERT is an abbreviation for which of the following methodologies?

(Multiple Choice)
4.8/5
(32)

Earned Value Management (EVM)has the capability to combine measurements of scope,schedule,and cost in a project.

(True/False)