CPM is an abbreviation for Critical Path Method.

(True/False)
4.9/5
(29)

The major goal of Critical Path analysis is to:

(Multiple Choice)
4.8/5
(41)

Breakthrough projects are those that provide fundamental improvements to existing products.

(True/False)
5.0/5
(40)

company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below: company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:   Using CPM,which activities have slack in this project? Using CPM,which activities have slack in this project?

(Multiple Choice)
4.8/5
(47)

The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.

(True/False)
4.8/5
(32)

The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.

(True/False)
4.8/5
(33)

One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.

(True/False)
4.9/5
(42)

Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

(Multiple Choice)
4.9/5
(36)

For an activity in a CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is true?

(Multiple Choice)
4.9/5
(44)

You have been placed in charge of a large project.Shortened communication lines are required to ensure quick resolution of problems as they arise.You recognize that the project is going to take a lot of time and require a lot of team pride,motivation,and commitment by all members.Which project management structure should you use in this situation?

(Multiple Choice)
4.8/5
(36)

One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.

(True/False)
4.8/5
(41)

The valuations in an Earned Value Management analysis must be either profits or revenue.

(True/False)
4.9/5
(36)

project can be subdivided into which of the following?

(Multiple Choice)
4.9/5
(41)

One of the advantages of a functional project organizational structure is that a team member can work on several projects.

(True/False)
4.9/5
(34)

In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

(Multiple Choice)
4.8/5
(40)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect)project cost? You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project direct costs are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect)project cost?

(Multiple Choice)
4.8/5
(33)

project starts out as which of the following?

(Multiple Choice)
4.9/5
(38)

Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost? Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost?

(Multiple Choice)
4.9/5
(32)

Project management software available today combines CPM and other scheduling aids,like Gantt charting,to aid in tracking progress of project completion.

(True/False)
4.8/5
(32)

Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.

(True/False)
4.8/5
(42)