Exam 5: Projects Manufacturing and Service Processes
Exam 1: Operations and Supply Chain Management71 Questions
Exam 2: Strategy and Sustainability48 Questions
Exam 3: Forecasting90 Questions
Exam 4: Strategic Capacity Management55 Questions
Exam 4: PART-A: Learning Curves49 Questions
Exam 5: Projects Manufacturing and Service Processes72 Questions
Exam 6: Manufacturing Processes56 Questions
Exam 6: PART-A: Break-Even Analysis9 Questions
Exam 7: Service Processes76 Questions
Exam 8: Sales and Operations Planning58 Questions
Exam 9: Material Requirements Planning81 Questions
Exam 10: Quality Management and Six-Sigma Supply Chain Processes and Analytics129 Questions
Exam 11: Inventory Management100 Questions
Exam 12: Lean Supply Chains71 Questions
Exam 13: Global Sourcing and Procurement64 Questions
Exam 14: Location, Logistics and Distribution54 Questions
Select questions type
disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.
(True/False)
4.7/5
(36)
Slack activity time is the difference between the early start and the late finish of a project activity time.
(True/False)
4.8/5
(42)
listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?
(Multiple Choice)
4.7/5
(26)
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.
(True/False)
4.8/5
(40)
The second step in managing a project is writing the Statement of Work.
(True/False)
4.8/5
(44)
simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project)?

(Multiple Choice)
4.8/5
(45)
Upper level management must decide between pure,functional,and matrix structures as ways to organize projects.
(True/False)
5.0/5
(37)
You have the following time and cost information below for use in a Time-Cost CPM Scheduling model.What are the three costs per unit of time to expedite each activity?


(Multiple Choice)
4.8/5
(37)
You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.
(True/False)
4.8/5
(29)
In a project analysis using three time estimates with more than one critical path existing,how does the project manager decide which variances to use in arriving at the probability of meeting the project due date?
(Multiple Choice)
4.8/5
(42)
company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:
Using CPM,which activities make up the critical path?

(Multiple Choice)
4.9/5
(39)
In a CPM analysis if you subtract the early start from the late start the result is the activity's slack time.
(True/False)
4.8/5
(34)
Showing 61 - 72 of 72
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)