Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Activities C,D,and E in the project represented by the network are to be hammocked.What is the activity length of the hammock activity?

(Multiple Choice)
4.9/5
(36)

What is the late start time for Activity B given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 -- B 6 A C 4 A D 5 B, C

(Multiple Choice)
4.9/5
(41)

In order to reduce the length of a project,it would be wise to shorten:

(Multiple Choice)
4.9/5
(30)

You must know the mean of an activity in order to determine its standard deviation.

(True/False)
4.7/5
(38)

Use the values in the table to calculate activity durations and variances for the project.What is the likelihood that the project takes between 60 and 55 days to complete? Activity Activity time Standard deviation Predecessor 12 3 8 2 9 1 5 1 12 0 10 0 7 2 9 3 , 15 2 , 8 2 11 3 7 2 ,

(Essay)
4.9/5
(32)

Burst activities are those with two or more successor activities.

(True/False)
4.8/5
(36)

Use the information in the table to determine the late start time for Activity E. Early Early Late Late Task Predecessor Duration Start Firish Start Firish 14 , 6 ,

(Multiple Choice)
4.9/5
(30)

Prior to creating a network,it is important to:

(Multiple Choice)
4.8/5
(35)

What is the background of CPM and PERT? What are the differences between the two techniques?

(Essay)
4.8/5
(26)

Construct a network using the information in the table and identify the critical path. Activity Time Predecessor A 4 B 6 A 9 A 11 16 , 4 ,

(Essay)
4.9/5
(41)

Use the information in the table to determine the slack time for Activity B. Early Early Late Late Task Predecesser Duration Start Firish Start Firish - 8 14 , 6 ,

(Multiple Choice)
4.9/5
(35)

What does a network diagram illustrate and why are they important in project management?

(Essay)
4.9/5
(30)

At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.

(True/False)
4.8/5
(35)

  -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
4.8/5
(39)

What is the early start time for Activity G given the activity times and precedence requirements shown in the table? Activity Time Predecessar A 5 -- B 7 -- 8 7 4 , , 7

(Multiple Choice)
4.9/5
(33)

Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? Activity Length Predecessor A 10 -- B 18 A C 14 A D 20 B, C

(Multiple Choice)
4.9/5
(33)

What is laddering and what advantages can be gained from its use in project management?

(Essay)
4.9/5
(34)

Concurrent activities are:

(Multiple Choice)
4.8/5
(31)

What is the float start time for Activity C given the activity times and precedence requirements shown in the table? Activity Tirne Predecessor 5 - 7 A 5 A 7 B, C

(Multiple Choice)
4.9/5
(40)

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project? Tirne Predecessor 7 8 13 8 7 6 6 11 12 ,,

(Multiple Choice)
4.7/5
(34)