Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Activity Predecessor Optirnistic Likely Pessirnistic A -- 4 6 10 B A 2 5 8 A 6 7 9 3 9 20 7 9 11 , 7 11 19
(Essay)
4.8/5
(29)
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
(Multiple Choice)
4.9/5
(30)
An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?
(Multiple Choice)
4.9/5
(36)
-Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

(Multiple Choice)
4.7/5
(31)
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
(True/False)
4.8/5
(31)
Which technique would accelerate the completion of a project?
(Multiple Choice)
4.8/5
(29)
What is the slack time for activity E? Early Early Late Late Task Predecessor Duration Start Firish Start Firish -- 14 , 6 ,
(Multiple Choice)
4.8/5
(44)
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
(Essay)
4.7/5
(30)
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? Tirne Predecessor 7 B 8 13 8 7 6 11 12 14 ,,
(Multiple Choice)
4.9/5
(38)
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? Activity Length Predecessor A 10 -- B 18 A 14 A 20 B, C
(Multiple Choice)
4.9/5
(34)
Based on the activity network pictured,what is the BEST statement?
(Multiple Choice)
4.9/5
(34)
Use the values in the table to calculate activity durations and variances for the project.What is the project deadline such that there is a 75% chance it is completed on time?
Activity Activity time Standard deviation Predecessor 12 3 8 2 9 1 5 1 12 0 10 0 7 2 9 3 , 15 2 , 8 2 11 3 7 2 ,
(Essay)
4.9/5
(30)
What is the early start time for Activity D given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 -- B 6 A 4 A 5 ,
(Multiple Choice)
4.8/5
(38)
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities E and F can be represented by a hammock activity.What are the duration and the early start time associated with this hammock activity? Tirne Predecessor 7 8 13 8 7 6 6 11 12 ,,
(Multiple Choice)
5.0/5
(37)
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 -- B 7 -- 8 A 7 A 4 8 , , 7
(Multiple Choice)
5.0/5
(34)
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path? Optimistic Most Likely Pessimistic Activity time time time Predecessor Corner Posts 4 5 6 - String Line 7 8 9 -- Dig Holes 10 12 14 Corner Posts Plant Posts 11 14 17 String Line Weld Top Bar 8 11 14 String Line Dig Holes, Plant Paint 9 11 13 Posts Tack Wire 9 12 16 Weld Top Bar
(Multiple Choice)
4.9/5
(37)
Preceding activities are those that must occur before others can be done.
(True/False)
4.8/5
(32)
Showing 61 - 80 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)