Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project takes more than 34 days? Activity Optimistic time Most Likely time Pessimistic time Predecessor Corner Posts 4 5 6 - String Line 7 8 9 - Dig Holes 10 12 14 Corner Posts Plant Posts 11 14 17 String Line Weld Top Bar 8 11 14 String Line Dig Holes, Plant Paint 9 11 13 Posts Tack Wire 9 12 16 Weld Top Bar

(Multiple Choice)
5.0/5
(31)

Summaries for some subsets of the activities identified in the overall project network are called:

(Multiple Choice)
4.8/5
(35)

These can be located by doing a backward pass through a network.

(Multiple Choice)
4.7/5
(36)

The variance of an activity is given by:

(Multiple Choice)
4.9/5
(29)

Use the information in the table to sketch the network and compute early and late start times. Activity Time Predecessor A 8 4 5 , 12 8 4 9 , 12 6 , 5 9 12 ,

(Essay)
4.8/5
(35)