Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project takes more than 34 days? Activity Optimistic time Most Likely time Pessimistic time Predecessor Corner Posts 4 5 6 - String Line 7 8 9 - Dig Holes 10 12 14 Corner Posts Plant Posts 11 14 17 String Line Weld Top Bar 8 11 14 String Line Dig Holes, Plant Paint 9 11 13 Posts Tack Wire 9 12 16 Weld Top Bar
(Multiple Choice)
5.0/5
(31)
Summaries for some subsets of the activities identified in the overall project network are called:
(Multiple Choice)
4.8/5
(35)
These can be located by doing a backward pass through a network.
(Multiple Choice)
4.7/5
(36)
Use the information in the table to sketch the network and compute early and late start times.
Activity Time Predecessor A 8 4 5 , 12 8 4 9 , 12 6 , 5 9 12 ,
(Essay)
4.8/5
(35)
Showing 101 - 105 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)