Exam 8: Scheduling Resources and Costs
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Resource leveling or smoothing can have all the following results on a project EXCEPT
(Multiple Choice)
4.9/5
(32)
Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available.Activity 3 is critical and has a duration of 5 days.Activity 4 has 2 days of slack and a duration of 2 days.How will he decide which activity should be scheduled first?
(Multiple Choice)
4.7/5
(34)
Many companies are ________ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.
(Short Answer)
4.8/5
(35)
In a resource-constrained project,the completion date is most likely to change.
(True/False)
4.8/5
(35)
Gene is trying to order the concrete needed to continue his project.However,the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?
(Multiple Choice)
4.8/5
(35)
Without a time-phased budget a good project schedule and cost control are impossible.
(True/False)
4.9/5
(29)
After resource leveling or smoothing one goal is that the amount of resources needed over the life of the project will be ___________.
(Short Answer)
4.7/5
(36)
Resources are adequate,but demand varies widely over the life of the project.Delaying noncritical activities to lower peak demand on resources is known as resource
(Multiple Choice)
4.7/5
(29)
Having one person responsible for performing several activities,all due at the same time,is an example of a(n)________ constraint.
(Short Answer)
4.8/5
(39)
Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time,she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?
(Multiple Choice)
4.9/5
(34)
If your project has spent $50,000 versus a budget of $45,000 and it is a week ahead of schedule,is it a certainty that your project is doing well? Explain why or why not.
(Not Answered)
This question doesn't have any answer yet
A special truck that George needs on his project has been scheduled on another project.This is an example of what type of resource constraint?
(Multiple Choice)
4.9/5
(38)
Why should project managers be cautious about using the splitting scheduling technique?
(Not Answered)
This question doesn't have any answer yet
Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
(True/False)
4.8/5
(34)
Identify and give an example of the three types of resource constraints.
(Not Answered)
This question doesn't have any answer yet
When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
(True/False)
4.7/5
(28)
All of the following are benefits of scheduling resources before project implementation EXCEPT
(Multiple Choice)
4.9/5
(36)
Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
(True/False)
4.9/5
(30)
When a project is classified as resource-constrained and a resource constraint exists,the project duration is typically __________.
(Short Answer)
4.8/5
(31)