An activity can include only one work package.

(True/False)
4.8/5
(40)

The backward pass determines project duration.

(True/False)
4.8/5
(40)

Which of the following will correctly calculate the total slack in an activity?

(Multiple Choice)
4.8/5
(37)

When completing a backward pass,you carry the LS to the next preceding activity to establish the LF,unless the next preceding activity is a burst activity,in which case you select

(Multiple Choice)
4.9/5
(34)

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

(Multiple Choice)
4.8/5
(38)

It is acceptable for arrows to cross one another in a network diagram.

(True/False)
4.8/5
(38)

If,for some reason,the project must be expedited to meet an earlier date,which of the following actions would the project manager take first?

(Multiple Choice)
4.9/5
(41)

When completing a forward pass,you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity.In this case you select the smallest early finish number of all its immediate predecessor activities.

(True/False)
4.9/5
(35)

A(n)_____________ calculates how late an activity can start and finish.

(Short Answer)
4.9/5
(39)

The activity time estimates used to build a project network are derived from ________.

(Short Answer)
4.7/5
(37)

A(n)________ is the minimum amount of time a dependent activity must be delayed to begin or end.

(Short Answer)
4.8/5
(38)

Which of the following correctly calculates the late start for an activity?

(Multiple Choice)
4.8/5
(36)

An activity cannot begin until ALL preceding connected activities have been completed.

(True/False)
4.9/5
(38)

Briefly describe looping and conditional statements and explain why they are not allowed when developing project networks.

(Not Answered)
This question doesn't have any answer yet
Ask our community

Only activities that occur at the end of a chain of activities can have free slack.

(True/False)
4.8/5
(38)

It is possible for a project network to have more than one critical path.

(True/False)
4.8/5
(38)

The _________ lag is the most typical type of lag that is encountered in developing networks.

(Short Answer)
5.0/5
(27)

The backward pass through a project network determines slack or how long an activity can be delayed without impacting the completion date of the project.

(True/False)
4.8/5
(29)

The forward pass in project network calculations determines all of the following EXCEPT

(Multiple Choice)
4.8/5
(40)

In a project network,________ indicate activity dependency and project flow.

(Short Answer)
4.8/5
(31)
Showing 41 - 60 of 94