Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles50 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS44 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects46 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick-Off45 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams46 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
All of the following conventions are widely adopted when project teams create the second level of the project Work Breakdown Structure (WBS)EXCEPT:
(Multiple Choice)
4.8/5
(42)
All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS)for a project EXCEPT:
(Multiple Choice)
4.9/5
(31)
A thorough scope definition process will often yield multiple project deliverables including intermediate project deliverables due before the project is complete.
(True/False)
4.7/5
(41)
The technique for dividing and subdividing the project scope and project deliverables into smaller,more manageable parts is called:
(Multiple Choice)
4.8/5
(34)
The best project scope statements are brief,succinct and limit their focus specifically to the work to be performed.
(True/False)
4.8/5
(36)
Plan scope management is the process of creating a project scope statement.
(True/False)
4.8/5
(32)
It is important to assign a unique number to every component in the project Work Breakdown Structure.
(True/False)
5.0/5
(37)
By using a systematic process of creating a Work Breakdown Structure,project team members can ensure that they remember all deliverables that need to be created.
(True/False)
4.8/5
(39)
The project scope planning processes include all of the following EXCEPT:
(Multiple Choice)
4.7/5
(29)
For each component in the Work Breakdown Structure (WBS),the WBS dictionary includes all the following fields that will be progressively elaborated EXCEPT:
(Multiple Choice)
4.8/5
(35)
It is helpful to list requirements and supporting information in a requirements traceability matrix.When requirements are complete,they should meet all of these criteria EXCEPT:
(Multiple Choice)
4.9/5
(36)
Identify and describe the three steps that the team should follow in order to define project scope and create a project scope statement.
(Essay)
4.7/5
(31)
Since work packages provide the basis for future project planning activities,they should be as detailed as possible.
(True/False)
4.9/5
(32)
What are some of the benefits of creating a Work Breakdown Structure (WBS)?
(Essay)
4.8/5
(39)
The approved version of a work product that can be changed only through formal change control procedures is called a ____:
(Multiple Choice)
4.8/5
(41)
Work Breakdown Structures can be displayed in a variety of formats including which of the following?
(Multiple Choice)
4.8/5
(36)
Which of the following statements concerning work packages is NOT correct?
(Multiple Choice)
4.9/5
(35)
Work Breakdown Structures typically include one or more intermediate levels.Which of the following statements correctly describe the nature of these intermediate levels?
(Multiple Choice)
4.8/5
(37)
The most conventional approach to create a Work Breakdown Structure is to adopt a "top-down" approach,which can be used when the project work is familiar to the team.
(True/False)
4.8/5
(31)
The Work Breakdown Structure (WBS)is a framework that will be used as a basis for further planning activities including all the following EXCEPT: