Exam 8: Scheduling Resources and Costs
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
These are all guidelines a project manager should consider when EXCEPT
(Multiple Choice)
4.9/5
(40)
When leveling schedules to overcome resource constraints, ___________ is increased.
(Multiple Choice)
4.9/5
(40)
When resource constraints are added to technical constraints the original project network may change as well as the completion date.
(True/False)
4.8/5
(30)
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
(True/False)
4.7/5
(32)
Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.
(True/False)
4.7/5
(41)
When a project is classified as resource-constrained and a resource constraint exists, the project duration is typically __________.
(Short Answer)
4.8/5
(40)
Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.
(True/False)
4.7/5
(32)
List and briefly describe the disadvantages of resource leveling or smoothing.
(Essay)
4.8/5
(30)
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.
(Multiple Choice)
4.8/5
(40)
The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
(True/False)
5.0/5
(30)
Having one person responsible for performing several activities, all due at the same time, is an example of a(n)________ constraint.
(Short Answer)
4.8/5
(36)
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.
(Short Answer)
4.8/5
(34)
In a resource-constrained project the second priority in assigning resources is usually given to activities with the
(Multiple Choice)
4.9/5
(35)
Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource __________.
(Short Answer)
4.9/5
(37)
Resource dependency takes priority over technological dependency but it does not violate it.
(True/False)
4.8/5
(36)
Why is a schedule not a schedule until resources have been assigned? Provide a real life example that illustrates your explanation.
(Essay)
4.9/5
(30)
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.We can assume that everything is going as planned and that we are under budget.
(True/False)
4.8/5
(36)
Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?
(Multiple Choice)
4.7/5
(40)
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization.She should first identify activities with the
(Multiple Choice)
4.9/5
(37)
Showing 81 - 100 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)