Exam 13: Project Scheduling: Pertcpm

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In PERT,the activity duration time is equal to:

(Multiple Choice)
4.8/5
(39)

Suppose that,after analyzing a PERT/CPM ntwork,the project manager finds that the project completion time is unacceptable.What are the manager's options?

(Essay)
4.9/5
(33)

Activities K,M and S immediately follow activity H,and their latest start times are 14,18,and 11.The latest finish time for activity H

(Multiple Choice)
4.8/5
(46)

Activities G,P,and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12,15,and 10,then the earliest start time for W

(Multiple Choice)
5.0/5
(32)

Three paths of a PERT network have these mean durations and variances in weeks: Path Mean Duration Variance 1 45 2.75 2 44 5.50 3 46 1.20 Which path offers the greatest risk of overrunning a contract deadline of 48 weeks?

(Essay)
4.8/5
(34)

The length of time an activity can be delayed without affecting the project completion time is the slack.

(True/False)
4.8/5
(29)

For the project represented below,determine the earliest and latest start and finish times for each activity as well as the expected overall completion time.  For the project represented below,determine the earliest and latest start and finish times for each activity as well as the expected overall completion time.    \begin{array} { c c c c c c c }  \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } \\ \hline \text { A } & 4 & & & & & \\ \text { B } & 3 & & & & & \\ \text { C } & 4 & & & & & \\ \text { D } & 2 & & & & & \\ \text { E } & 5 & & & & & \\ \text { F } & 2 & & & & & \\ \text { G } & 5 & & & & & \\ \text { H } & 6 & & & & \end{array} Activity Duration ES EF LS LF Slack A 4 B 3 C 4 D 2 E 5 F 2 G 5 H 6

(Essay)
4.9/5
(34)

The earliest finish time for the final activity is the project duration.

(True/False)
4.8/5
(41)

Activities following a node

(Multiple Choice)
4.9/5
(28)

Explain how and why all successor activities must be considered when finding the latest finish time.

(Essay)
4.9/5
(38)

When activity times are uncertain,total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.

(True/False)
4.7/5
(36)

A path through a project network must reach every node.

(True/False)
4.9/5
(31)

A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below. A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below.     Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in fewer than 25 weeks more or less than 50%? A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below.     Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in fewer than 25 weeks more or less than 50%? Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in fewer than 25 weeks more or less than 50%?

(Essay)
4.8/5
(37)

In deciding which activities to crash,one must

(Multiple Choice)
4.8/5
(36)

When activity times are uncertain,

(Multiple Choice)
4.9/5
(38)

For an activity with more than one immediate successor activity,its latest-finish time is equal to the

(Multiple Choice)
4.9/5
(28)

Consider a project that has been modeled as follows: Activity Immediate Predecessors Duration (hr) A \@cdots 7 B \@cdots 10 C A 4 D A 30 E A 7 F B,C 12 G B,C 15 H E,F 11 I E,F 25 J E,F 6 K D, H 21 L G,J 25 a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path. b.Can activities E and G be performed simultaneously without delaying the minimum project completion time? c.Can one person perform A, G, and I without delaying the project? d.By how much can activities G and L be delayed without delaying the entire project? e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.

(Essay)
4.8/5
(31)

A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below. A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below.     Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in more than 28 weeks more or less than 50%? A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below.     Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in more than 28 weeks more or less than 50%? Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in more than 28 weeks more or less than 50%?

(Essay)
4.9/5
(34)

The main difference between CPM and PERT is:

(Multiple Choice)
4.8/5
(39)

Activities with zero slack

(Multiple Choice)
4.9/5
(39)
Showing 21 - 40 of 66
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)