Exam 13: Project Scheduling: Pertcpm
Exam 1: Introduction61 Questions
Exam 2: Introduction to Probability66 Questions
Exam 3: Probability Distributions66 Questions
Exam 4: Decision Analysis64 Questions
Exam 5: Utility and Game Theory67 Questions
Exam 6: Times Series Analysis and Forecasting63 Questions
Exam 7: Introduction to Linear Programming60 Questions
Exam 8: Linear Programming: Sensitivity Analysis and Interpretation of Solution64 Questions
Exam 9: Linear Programming Applications in Marketing, Finance, and Operations Management60 Questions
Exam 10: Distribution and Network Models67 Questions
Exam 11: Integer Linear Programming61 Questions
Exam 12: Advanced Optimization Applications56 Questions
Exam 13: Project Scheduling: Pertcpm66 Questions
Exam 14: Inventory Models66 Questions
Exam 15: Waiting Line Models62 Questions
Exam 16: Simulation62 Questions
Exam 17: Markov Processes55 Questions
Select questions type
Suppose that,after analyzing a PERT/CPM ntwork,the project manager finds that the project completion time is unacceptable.What are the manager's options?
(Essay)
4.9/5
(33)
Activities K,M and S immediately follow activity H,and their latest start times are 14,18,and 11.The latest finish time for activity H
(Multiple Choice)
4.8/5
(46)
Activities G,P,and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12,15,and 10,then the earliest start time for W
(Multiple Choice)
5.0/5
(32)
Three paths of a PERT network have these mean durations and variances in weeks: Path Mean Duration Variance 1 45 2.75 2 44 5.50 3 46 1.20 Which path offers the greatest risk of overrunning a contract deadline of 48 weeks?
(Essay)
4.8/5
(34)
The length of time an activity can be delayed without affecting the project completion time is the slack.
(True/False)
4.8/5
(29)
For the project represented below,determine the earliest and latest start and finish times for each activity as well as the expected overall completion time.
Activity Duration ES EF LS LF Slack A 4 B 3 C 4 D 2 E 5 F 2 G 5 H 6

(Essay)
4.9/5
(34)
The earliest finish time for the final activity is the project duration.
(True/False)
4.8/5
(41)
Explain how and why all successor activities must be considered when finding the latest finish time.
(Essay)
4.9/5
(38)
When activity times are uncertain,total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.
(True/False)
4.7/5
(36)
A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below.
Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in fewer than 25 weeks more or less than 50%?


(Essay)
4.8/5
(37)
For an activity with more than one immediate successor activity,its latest-finish time is equal to the
(Multiple Choice)
4.9/5
(28)
Consider a project that has been modeled as follows: Activity Immediate Predecessors Duration (hr) A \@cdots 7 B \@cdots 10 C A 4 D A 30 E A 7 F B,C 12 G B,C 15 H E,F 11 I E,F 25 J E,F 6 K D, H 21 L G,J 25
a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path.
b.Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.Can one person perform A, G, and I without delaying the project?
d.By how much can activities G and L be delayed without delaying the entire project?
e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.
(Essay)
4.8/5
(31)
A project network is shown below.Use a forward and a backward pass to determine the critical path,and then fill out the table below.
Now assume that the times listed are only the expected times instead of being fixed times.Is the probability of being finished in more than 28 weeks more or less than 50%?


(Essay)
4.9/5
(34)
Showing 21 - 40 of 66