Exam 8: Facility and Work Designs
Exam 1: Goods, Services, and Operations Management81 Questions
Exam 2: Value Chains87 Questions
Exam 3: Measuring Performance in Operations98 Questions
Exam 4: Operations Strategy82 Questions
Exam 5: Technology and Operations Management77 Questions
Exam 6: Goods and Service Design118 Questions
Exam 7: Process Selection, Design, and Analysis116 Questions
Exam 8: Facility and Work Designs92 Questions
Exam 9: Supply Chain Design87 Questions
Exam 10: Capacity Management89 Questions
Exam 11: Forecasting and Demand Planning95 Questions
Exam 12: Managing Inventories117 Questions
Exam 13: Resource Management106 Questions
Exam 14: Operations Scheduling and Sequencing79 Questions
Exam 15: Quality Management81 Questions
Exam 15: Appendix: Quality Management56 Questions
Exam 16: Quality Control and Spc110 Questions
Exam 16: Appendix: Queuing Analysis38 Questions
Exam 17: Appendix: Modeling Using Linear Programming41 Questions
Exam 17: Lean Operating Systems84 Questions
Exam 18: Appendix: Simulation40 Questions
Exam 18: Project Management108 Questions
Exam 19: Appendix: Decision Analysis44 Questions
Select questions type
A small electronics company assembles microchips for use in computers, printers and fax machines. They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the longest-task-time heuristic. The demand for microchips is 70 per hour, and the productive time per hour is 52 minutes. The following table provides details on their operation. Task Time (n minutes) Predecessor(s) A 0.54 none B 0.34 A C 0.11 A D 0.09 A E 0.43 B, C F 0.22 D G 0.62 E H 0.35 F, G I 0.21 H J 0.57 H K 0.33 I. J
a.What is the cycle time?
b.What is the theoretical minimum number of workstations?
c.What tasks go into the first workstation?
d.How many workstations are needed for the entire line?
e.What is the assembly-line efficiency?
Free
(Essay)
4.9/5
(32)
Correct Answer:
a.Cycle time = 52 min per hr./70 units per hr. = 0.742 minutes/unit
b.Sum of task times = 3.81 minutes
Theoretical minimum number of workstations
= [(3.81 min/unit)[(70 units/hour)/(52 min/hour)]] = 5.134 = 6 workstations
c.Tasks A ,C, and D
d.
e.Efficiency = t/(N * CT) = 3.81/(7 * 0.742) = 3.81/5.18 = 0.735 = 73.552%
Which one of the following statements is TRUE regarding the BankUSA: Cash Movement case study?
Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
A
Because of precedence relationships in a network, assembly-line efficiencies will generally be very high.
Free
(True/False)
4.9/5
(39)
Correct Answer:
False
An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 39 minutes. The longest activity is 2.2 minutes and the shortest is 0.8 minutes. The line will operate for 450 minutes per day. What is the assembly-line efficiency with 11 stations and a product produced every 5 minutes?
(Multiple Choice)
4.8/5
(36)
Cycle time in assembly-line balancing is the maximum amount of time it takes to process a part at some workstation along the line.
(True/False)
4.7/5
(34)
In a _____ team, members communicate by computer, take turns as leaders, and join and leave the team as necessary.
(Multiple Choice)
4.7/5
(35)
Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate) is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations.
SHAPE \* MERGEFORMAT
Worksheet for assembly-line balancing problem
Workstation Assigned Tasks Total Time Idle Time A B C D E F Use the previous assembly-line balancing (ALB) information to answer Questions .
-What is the cycle time?


(Multiple Choice)
4.9/5
(39)
A Gallup study showed that workers who are allowed to personalize their workplaces were no more productive than those who are not allowed.
(True/False)
4.9/5
(33)
_____ is vertical expansion of job duties to give a worker more responsibility.
(Multiple Choice)
4.9/5
(33)
The facility layout in a library would most likely be a process layout.
(True/False)
4.8/5
(33)
A product requires the following tasks to make it on an assembly line. Assume 7.6 hours per workday and 5 workdays per week. Task Time (n minutes) Predecessor(s) A 10 none B 14 A C 12 none D 8 none E 11 C F 17 C, D G 20 B H 9 E I 13 D J 15 G, H K 17 H, I L 8 J M 10 I N 15 K, L, M
a.Using only the information given, what would be the maximum output per day that can be achieved?
b.Assume that the activities have been assigned to five workstations. What is the line efficiency for a cycle time of 40 seconds?
(Essay)
4.7/5
(32)
Which of the following statements is NOT true about assembly lines?
(Multiple Choice)
4.8/5
(33)
In a product layout, a breakdown of one piece of equipment will not cause the entire process to shut down.
(True/False)
4.8/5
(37)
A _____ layout is an arrangement based on the sequence of operations that are performed during the manufacturing of a good or delivery of a service.
(Multiple Choice)
4.9/5
(35)
The twelve tasks necessary to assemble a food blender are listed below. The time to perform each task and the tasks that must immediately precede are also listed. 200 blenders are needed per hour and 50 minutes per hour are productive:
Task Time (in minutes) Predecessors Task Time (in minutes) Predecessors A 0.20 none G 0.08 E, F B 0.05 none H 0.12 none C 0.15 none I 0.05 none D 0.06 none J 0.12 H, I, G E 0.03 A, B K 0.15 J F 0.16 C, D L 0.08 K
a.Compute the cycle time per unit in minutes.
b.Compute the minimum number of workstations required.
c.Use the longest-task-time heuristic to balance the assembly line.
d.Compute the efficiency of your assembly line.
(Essay)
4.8/5
(32)
The eleven tasks necessary to assemble an MP3 player along with their time (in seconds) and immediate predecessor(s) is given below:
Task Time (n minutes) Predecessor(s) A 40 none B 15 none C 35 none D 12 A, B E 27 B, C F 29 D G 60 D, E H 30 E I 14 F, G J 22 G, H K 43 I, J Total 327 The company wants to produce 600 units in a 9-hour day.
-The cycle time is _____ seconds.
(Multiple Choice)
4.9/5
(23)
Showing 1 - 20 of 92
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)