Exam 18: Project Management
Exam 1: Goods, Services, and Operations Management81 Questions
Exam 2: Value Chains87 Questions
Exam 3: Measuring Performance in Operations98 Questions
Exam 4: Operations Strategy82 Questions
Exam 5: Technology and Operations Management77 Questions
Exam 6: Goods and Service Design118 Questions
Exam 7: Process Selection, Design, and Analysis116 Questions
Exam 8: Facility and Work Designs92 Questions
Exam 9: Supply Chain Design87 Questions
Exam 10: Capacity Management89 Questions
Exam 11: Forecasting and Demand Planning95 Questions
Exam 12: Managing Inventories117 Questions
Exam 13: Resource Management106 Questions
Exam 14: Operations Scheduling and Sequencing79 Questions
Exam 15: Quality Management81 Questions
Exam 15: Appendix: Quality Management56 Questions
Exam 16: Quality Control and Spc110 Questions
Exam 16: Appendix: Queuing Analysis38 Questions
Exam 17: Appendix: Modeling Using Linear Programming41 Questions
Exam 17: Lean Operating Systems84 Questions
Exam 18: Appendix: Simulation40 Questions
Exam 18: Project Management108 Questions
Exam 19: Appendix: Decision Analysis44 Questions
Select questions type
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
Project Immediate Optimistic Most Likely Pessimistic Expected Activity Activity Predecessor(s) Time Time Time Time Variance A none 2 5 14 B none 8 11 14 C A 5 7 9 D A 6 9 12 E B, C, D 1 3 5 Draw the project network here. BLANK SPACES
Activity OT MLT PT ET AV A 2 5 14 6.00 4.00 B 8 11 14 11.00 1.00 C 5 7 9 7.00 0.44 D 6 9 12 9.00 1.00 F 1 3 5 3.00 0.44
-Using the table for the advertising and promotion project, if the expected time (not the most likely time) for activity B is changed to 18 weeks, by how many weeks will the project's expected completion time increase?
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
D
You are responsible for managing an advertising project with the following activities (times are given in weeks).
Draw the project network here. BLANK SPACES
-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?
Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
A
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
Project Immediate Optimistic Most Likely Pessimistic Expected Activity Activity Predecessor(s) Time Time Time Time Variance A none 2 5 14 B none 8 11 14 C A 5 7 9 D A 6 9 12 E B, C, D 1 3 5 Draw the project network here. BLANK SPACES
Activity OT MLT PT ET AV A 2 5 14 6.00 4.00 B 8 11 14 11.00 1.00 C 5 7 9 7.00 0.44 D 6 9 12 9.00 1.00 F 1 3 5 3.00 0.44
-Using the table for the advertising and promotion project, what is the probability percentage that the project will be completed within 16 weeks?
Free
(Multiple Choice)
4.7/5
(33)
Correct Answer:
A
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
Project Immediate Optimistic Most Likely Pessimistic Expected Activity Activity Predecessor(s) Time Time Time Time Variance A none 2 5 14 B none 8 11 14 C A 5 7 9 D A 6 9 12 E B, C, D 1 3 5 Draw the project network here. BLANK SPACES
Activity OT MLT PT ET AV A 2 5 14 6.00 4.00 B 8 11 14 11.00 1.00 C 5 7 9 7.00 0.44 D 6 9 12 9.00 1.00 F 1 3 5 3.00 0.44
-Using the table for the advertising and promotion project, which activity has the largest slack, and how large is that slack?
(Multiple Choice)
4.8/5
(32)
The network below represents a project being analyzed by the Critical Path Method.
a.What activity must be on the critical path, regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?

(Essay)
4.7/5
(32)
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
(True/False)
4.8/5
(36)
The following network shows the activities on the circles or nodes. Time estimates are in weeks.
Complete the following table:
Activity Time Earliest Start Earliest Finish Latest Start Latest Finish Slack On Critical Path? A

(Essay)
4.9/5
(30)
Immediate predecessors are activities that must be completed immediately before an activity may start.
(True/False)
4.8/5
(33)
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
Activity Immediate Predecessor(s) Normal Time in weeks Crash Time in weeks Normal Cost Crash Cost A None 2 2 \ 15,000 \ 15,000 B None 1 1 \ 12,000 \ 12,000 C A, B 5 3 \ 18,000 \ 24,000 D A, B 4 2 \ 12,000 \ 16,000 E C, D 2 1 \ 22,000 \ 23,500 F D 4 3 \ 32,000 \ 36,000 G E, F 3 2 \ 19,000 \ 20,000 Draw the project network in the space below if you want. BLANK SPACES
-Britt is managing this project, and his bossRose gives him $5,000 to speed up the original completion time (i.e., project improvement dollars). The best action is to:
(Multiple Choice)
4.8/5
(40)
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
Activity Immediate Predecessor(s) Normal Time in weeks Crash Time in weeks Normal Cost Crash Cost A None 2 2 \ 15,000 \ 15,000 B None 1 1 \ 12,000 \ 12,000 C A, B 5 3 \ 18,000 \ 24,000 D A, B 4 2 \ 12,000 \ 16,000 E C, D 2 1 \ 22,000 \ 23,500 F D 4 3 \ 32,000 \ 36,000 G E, F 3 2 \ 19,000 \ 20,000 Draw the project network in the space below if you want. BLANK SPACES
-The total minimum crash cost only for the project to achieve a two-week earlier completion time from the original project completion time is:
(Multiple Choice)
4.8/5
(42)
You are responsible for managing a project with the following activities (times are given in weeks):
-What is the critical path and expected completion time for this project?
(Multiple Choice)
4.9/5
(34)
Which of the following statements is TRUE of the activities not on the critical path?
(Multiple Choice)
4.8/5
(24)
A Gantt chart is a useful tool for allocating limited resources among project activities.
(True/False)
4.8/5
(31)
In the critical path method (CPM), there can only be one critical path.
(True/False)
4.9/5
(32)
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
Immediate Optimistic Most Likely Pessimistic Activity Predecessors a none 4 6 7 1 2 3 5 5 5 7 9 12 2 4 8 d 6 9 10 Solutions are at the end of questions
-What is the slack time for Activity B?
(Multiple Choice)
4.8/5
(24)
The Critical path method (CPM) and Project Evaluation and Review Technique (PERT) are not likely to be used in marketing.
(True/False)
5.0/5
(33)
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
Activity Immediate Predecessor(s) Activity Time in weeks A None 1 B A 2 C A 3 D A, B 4 E C, D 3 F D, E 2
-If activity C is delayed by three weeks, the revised earliest project completion time is:
(Multiple Choice)
4.8/5
(31)
Preparation of annual reports does not require project management techniques.
(True/False)
4.8/5
(31)
To compute the critical path, all nodes in the network are assigned an earliest starting time of zero.
(True/False)
4.9/5
(39)
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
Immediate Optimistic Most Likely Pessimistic Activity Predecessors a none 4 6 7 1 2 3 5 5 5 7 9 12 2 4 8 d 6 9 10 Solutions are at the end of questions
-What is the critical path
(Multiple Choice)
4.8/5
(36)
Showing 1 - 20 of 108
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)