Exam 14: Operations Scheduling and Sequencing

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The time to rest and travel between games for baseball umpire crews is an important factor in developing their schedule.

Free
(True/False)
4.9/5
(31)
Correct Answer:
Verified

True

Scheduling and sequencing methods used in manufacturing are more beneficial in low-contact, than high-contact, service processes.

Free
(True/False)
4.7/5
(40)
Correct Answer:
Verified

True

The sequencing rule that minimizes the maximum number of jobs that are past due from a given set of jobs is:

Free
(Multiple Choice)
4.8/5
(43)
Correct Answer:
Verified

B

Which one of the following statements about the Balloons Aloha case study on scheduling and sequencing is TRUE?

(Multiple Choice)
4.9/5
(35)

Flow time is the amount of time a job spends in a shop or factory.

(True/False)
4.8/5
(37)

Like the shortest processing time (SPT) rule, the earliest due date (EDD) rule minimizes the average flow time.

(True/False)
5.0/5
(35)

Scheduling applies to all aspects of the value chain.

(True/False)
4.8/5
(34)

A tardiness measure can be either zero (0) or a positive number.

(True/False)
4.9/5
(37)

Telling an umpire crew to work baseball games in Chicago, then Milwaukee, and then Cleveland is an example of a sequence.

(True/False)
4.9/5
(35)

An airplane repair facility has a contract to repair cargo aircrafts for a regional airline. There are 62 planes in the airline company's fleet of planes. Because of the punishing workload, the planes require a considerable amount of maintenance. The repair facility is trying to determine how to schedule the needed repairs. They want to compare the shortest processing time (SPT) rule and the first come, first served (FCFS) rule. Currently, the following planes need repair and are in the repair facility (data given is in the order of plane arrival, only one plane is worked on at a time, and the shop is open 24 hours a day, 7 days a week). Plane Estimated repair time A342 4 hours B554 26 hours C222 2 hours D876 16 hours E211 9 hours F887 6 hours a.In what order should the planes be repaired using the shortest processing time rule (use first letter of plane)? b.What is the average time (in hours) in the shop using the shortest processing time (SPT) rule? c.What is the average time (in hours) in the shop using the first come, first served (FCFS) rule?

(Essay)
4.9/5
(39)

Johnson's sequencing rule is used to sequence:

(Multiple Choice)
4.9/5
(30)

The table below includes processing times and due dates for five jobs. Processing Days Due Job Time (days) From Today A 16 24 B 23 30 C 22 40 D 8 28 E 10 18 -Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.

(Multiple Choice)
4.8/5
(33)

The numerical difference between the completion time and the due date is called:

(Multiple Choice)
4.8/5
(35)

UPS, the world's largest package delivery company, is highly dependent on scheduling but not sequencing.

(True/False)
4.8/5
(35)

Tardiness measures the amount of time by which the completion time exceeds the due date.

(True/False)
4.9/5
(39)

Describe the algorithm that defines Johnson's sequencing rule for the two-resource sequencing problem.

(Essay)
4.7/5
(30)

The table below includes processing times and due dates for five jobs. Processing Days Due Job Time (days) From Today A 16 24 B 23 30 C 22 40 D 8 28 E 10 18 -Using the earliest due date (EDD) rule, the average lateness for the five jobs is _____.

(Multiple Choice)
4.9/5
(37)

Which of the following is an example of a situation for which a Gantt chart would be appropriate?

(Multiple Choice)
4.8/5
(28)

Scheduling refers to determining the order in which jobs or tasks are processed.

(True/False)
4.8/5
(37)

Scheduling refers to specifying:

(Multiple Choice)
4.9/5
(29)
Showing 1 - 20 of 79