Exam 15: Project Management Online

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Slack represents the amount of time by which an activity can be delayed without delaying the entire project,assuming that

(Multiple Choice)
4.8/5
(34)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessor Activities A 1 − B 4 A C 3 B D 3 C E 2 B F 4 E G 2 D,F -Refer to Exhibit 15.4.The following spreadsheet was developed to determine the earliest start times and latest start times for the project.Based on the data in the spreadsheet,which activities are on the critical path? A B C D E F G H I 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity 2 5 7 5 7 0 7 Activity F 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0

(Essay)
4.7/5
(32)

What are the immediate predecessors of activity D in this network? What are the immediate predecessors of activity D in this network?

(Multiple Choice)
4.8/5
(37)

Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.  Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     \begin{array} { | c | c | c | c | c | c | c | c | c | c | }  \hline & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } & \text { F } & \text { G } & \text { H } & \text { I } \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessar } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & \text { I } & 4 & \text { I } & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline \text { 6 } & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline8 & \text { G } & \text { Activity G } & \text { E ,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}  -Refer to Exhibit 15.1.What array formula is placed in cell H5 to calculate the Latest Finish Time? A B C D E F G H I 1 Activity Description Predecessar Time EST EFT LST LFT Slack 2 A Activity A 4 I 4 I 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E ,F 3 16 19 16 19 -Refer to Exhibit 15.1.What array formula is placed in cell H5 to calculate the Latest Finish Time?

(Multiple Choice)
4.7/5
(37)

Which of the following correctly describes the focus of the Critical Path Method CPM)?

(Multiple Choice)
4.9/5
(40)
Showing 61 - 65 of 65