Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis74 Questions
Exam 2: Introduction to Optimization and Linear Programming73 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet75 Questions
Exam 4: Sensitivity Analysis and the Simplex Method77 Questions
Exam 5: Network Modeling84 Questions
Exam 6: Integer Linear Programming88 Questions
Exam 7: Goal Programming and Multiple Objective Optimization65 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization69 Questions
Exam 9: Regression Analysis82 Questions
Exam 10: Data Mining102 Questions
Exam 11: Time Series Forecasting81 Questions
Exam 12: Introduction to Simulation Using Analytic Solver Platform70 Questions
Exam 13: Queuing Theory87 Questions
Exam 14: Decision Analysis116 Questions
Exam 15: Project Management Online65 Questions
Select questions type
Slack represents the amount of time by which an activity can be delayed without delaying the entire project,assuming that
(Multiple Choice)
4.8/5
(34)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity
Days Required
Predecessor Activities
A 1 −
B 4 A
C 3 B
D 3 C
E 2 B
F 4 E
G 2 D,F
-Refer to Exhibit 15.4.The following spreadsheet was developed to determine the earliest start times and latest start times for the project.Based on the data in the spreadsheet,which activities are on the critical path?
A B C D E F G H I 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity 2 5 7 5 7 0 7 Activity F 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0
(Essay)
4.7/5
(32)
What are the immediate predecessors of activity D in this network? 

(Multiple Choice)
4.8/5
(37)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
A B C D E F G H I 1 Activity Description Predecessar Time EST EFT LST LFT Slack 2 A Activity A 4 I 4 I 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E ,F 3 16 19 16 19
-Refer to Exhibit 15.1.What array formula is placed in cell H5 to calculate the Latest Finish Time?

(Multiple Choice)
4.7/5
(37)
Which of the following correctly describes the focus of the Critical Path Method CPM)?
(Multiple Choice)
4.9/5
(40)
Showing 61 - 65 of 65
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)