Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity. A B C D E F G H 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 5 6000 3 8000 2 1000 4 - 3 18000 2 19000 1 1000 5 - 4 14000 2 19000 2 2500 6 D - 7 6000 4 9000 3 1000 7 E - 6 9000 1 14000 5 1000 8 F - 5 12000 3 14000 2 1000 9 G - 4 3500 2 7500 2 2000 Costs  Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.   \begin{array}{|c|c|c|c|c|c|c|c|c|}  \hline& \text { A } & \text { B } & \text { C } & \text { D } & \text { E } & \text { F } & \text { G } & \text { H } \\ \hline 1 & & & \text { Normal } & & \text { Crash } & & \text { Allowable } & \text { Crash Cost } \\ \hline 2 & \text { Activity } & \text { Description } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } & \text { Crash Days } & \text { Per Day } \\\hline 3 & \mathrm{~A} & - & 5 & 6000 & 3 & 8000 & 2 & 1000 \\ \hline 4 & \mathrm{~B} & - & 3 & 18000 & 2 & 19000 & 1 & 1000 \\ \hline 5 & \mathrm{C} & - & 4 & 14000 & 2 & 19000 & 2 & 2500 \\\hline 6 & \text { D } & - & 7 & 6000 & 4 & 9000 & 3 & 1000 \\ \hline 7 & \text { E } & - & 6 & 9000 & 1 & 14000 & 5 & 1000 \\ \hline 8 & \text { F } & - & 5 & 12000 & 3 & 14000 & 2 & 1000 \\ \hline 9 & \text { G } & - & 4 & 3500 & 2 & 7500 & 2 & 2000 \\ \hline&\text { Costs }\\ \hline \end{array}    -Refer to Exhibit 15.5.What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day? -Refer to Exhibit 15.5.What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?

Free
(Essay)
4.9/5
(29)
Correct Answer:
Verified

=F3-D3)/C3-E3)or F3-D3)/G3

The critical path in PERT analysis is the path with the

Free
(Multiple Choice)
4.8/5
(25)
Correct Answer:
Verified

B

For an activity with duration t,slack can be calculated as

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
Verified

A

In CPM,the duration of the project

(Multiple Choice)
4.7/5
(32)

Which activities have slack in the following diagram? Which activities have slack in the following diagram?

(Multiple Choice)
4.8/5
(35)

There are various similarities between the CPM and PERT methods.Which of the following is not one of those similarities?

(Multiple Choice)
4.8/5
(34)

The term "time zero" identifies

(Multiple Choice)
4.9/5
(41)

What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day? B D E F 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 4 12000 2 14000 2 1000 4 B - 3 6000 2 6500 1 500 5 C - 2 18000 1 19000 1 1000 6 D - 7 14000 4 20000 3 2000 7 E - 2 3500 1 4000 1 500 8 F - 2 6000 1 7500 1 1500 9 G - 3 9000 1 12000 2 1500 COSTS

(Multiple Choice)
4.9/5
(36)

The longest path through a network is comprised of the activities.

(Multiple Choice)
5.0/5
(28)

If we are employing Activity-On-Node AON)network design,the arcs in the network diagram represent

(Multiple Choice)
4.8/5
(38)

What is the earliest start time for activity D in the following diagram? What is the earliest start time for activity D in the following diagram?

(Multiple Choice)
4.8/5
(30)

Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity. A B C D E F G H 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 5 6000 3 8000 2 1000 4 - 3 18000 2 19000 1 1000 5 - 4 14000 2 19000 2 2500 6 D - 7 6000 4 9000 3 1000 7 E - 6 9000 1 14000 5 1000 8 F - 5 12000 3 14000 2 1000 9 G - 4 3500 2 7500 2 2000 Costs  Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.   \begin{array}{|c|c|c|c|c|c|c|c|c|}  \hline& \text { A } & \text { B } & \text { C } & \text { D } & \text { E } & \text { F } & \text { G } & \text { H } \\ \hline 1 & & & \text { Normal } & & \text { Crash } & & \text { Allowable } & \text { Crash Cost } \\ \hline 2 & \text { Activity } & \text { Description } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } & \text { Crash Days } & \text { Per Day } \\\hline 3 & \mathrm{~A} & - & 5 & 6000 & 3 & 8000 & 2 & 1000 \\ \hline 4 & \mathrm{~B} & - & 3 & 18000 & 2 & 19000 & 1 & 1000 \\ \hline 5 & \mathrm{C} & - & 4 & 14000 & 2 & 19000 & 2 & 2500 \\\hline 6 & \text { D } & - & 7 & 6000 & 4 & 9000 & 3 & 1000 \\ \hline 7 & \text { E } & - & 6 & 9000 & 1 & 14000 & 5 & 1000 \\ \hline 8 & \text { F } & - & 5 & 12000 & 3 & 14000 & 2 & 1000 \\ \hline 9 & \text { G } & - & 4 & 3500 & 2 & 7500 & 2 & 2000 \\ \hline&\text { Costs }\\ \hline \end{array}    -Refer to Exhibit 15.5.What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts? -Refer to Exhibit 15.5.What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?

(Essay)
4.8/5
(29)

Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.  Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     \begin{array} { | c | c | c | c | c | c | c | c | c | c | }  \hline & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } & \text { F } & \text { G } & \text { H } & \text { I } \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessar } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & \text { I } & 4 & \text { I } & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline \text { 6 } & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline8 & \text { G } & \text { Activity G } & \text { E ,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}  -Refer to Exhibit 15.1.What values are placed in cell C5 of the spreadsheet? A B C D E F G H I 1 Activity Description Predecessar Time EST EFT LST LFT Slack 2 A Activity A 4 I 4 I 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E ,F 3 16 19 16 19 -Refer to Exhibit 15.1.What values are placed in cell C5 of the spreadsheet?

(Multiple Choice)
4.8/5
(34)

For an activity with duration t,slack can be calculated as

(Multiple Choice)
5.0/5
(43)

What is the latest finish time for activity D in the following diagram? What is the latest finish time for activity D in the following diagram?

(Multiple Choice)
4.8/5
(49)

If the following project must be completed by day 18 at minimum cost how do we change the LP model? If the following project must be completed by day 18 at minimum cost how do we change the LP model?

(Multiple Choice)
4.8/5
(35)

CPM and PERT differ because of

(Multiple Choice)
4.7/5
(30)

In project control charts,the horizontal bars are shaded to indicate

(Multiple Choice)
4.8/5
(39)

Which of the following definitions correctly defines the acronym,PERT?

(Multiple Choice)
5.0/5
(31)

Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set off activities: Activity Predecessor Activities Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set off activities: Activity Predecessor Activities    A --- B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,F,G -Refer to Exhibit 15.6.Is it necessary to draw an arc from the node for activity F to the node for activity I? A --- B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,F,G -Refer to Exhibit 15.6.Is it necessary to draw an arc from the node for activity F to the node for activity I?

(Not Answered)
This question doesn't have any answer yet
Ask our community
Showing 1 - 20 of 65
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)