Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis74 Questions
Exam 2: Introduction to Optimization and Linear Programming73 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet75 Questions
Exam 4: Sensitivity Analysis and the Simplex Method77 Questions
Exam 5: Network Modeling84 Questions
Exam 6: Integer Linear Programming88 Questions
Exam 7: Goal Programming and Multiple Objective Optimization65 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization69 Questions
Exam 9: Regression Analysis82 Questions
Exam 10: Data Mining102 Questions
Exam 11: Time Series Forecasting81 Questions
Exam 12: Introduction to Simulation Using Analytic Solver Platform70 Questions
Exam 13: Queuing Theory87 Questions
Exam 14: Decision Analysis116 Questions
Exam 15: Project Management Online65 Questions
Select questions type
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
A B C D E F G H 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 5 6000 3 8000 2 1000 4 - 3 18000 2 19000 1 1000 5 - 4 14000 2 19000 2 2500 6 D - 7 6000 4 9000 3 1000 7 E - 6 9000 1 14000 5 1000 8 F - 5 12000 3 14000 2 1000 9 G - 4 3500 2 7500 2 2000 Costs
-Refer to Exhibit 15.5.What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?

Free
(Essay)
4.9/5
(29)
Correct Answer:
=F3-D3)/C3-E3)or F3-D3)/G3
The critical path in PERT analysis is the path with the
Free
(Multiple Choice)
4.8/5
(25)
Correct Answer:
B
For an activity with duration t,slack can be calculated as
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
A
There are various similarities between the CPM and PERT methods.Which of the following is not one of those similarities?
(Multiple Choice)
4.8/5
(34)
What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day?
B D E F 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 4 12000 2 14000 2 1000 4 B - 3 6000 2 6500 1 500 5 C - 2 18000 1 19000 1 1000 6 D - 7 14000 4 20000 3 2000 7 E - 2 3500 1 4000 1 500 8 F - 2 6000 1 7500 1 1500 9 G - 3 9000 1 12000 2 1500 COSTS
(Multiple Choice)
4.9/5
(36)
The longest path through a network is comprised of the activities.
(Multiple Choice)
5.0/5
(28)
If we are employing Activity-On-Node AON)network design,the arcs in the network diagram represent
(Multiple Choice)
4.8/5
(38)
What is the earliest start time for activity D in the following diagram? 

(Multiple Choice)
4.8/5
(30)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
A B C D E F G H 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 5 6000 3 8000 2 1000 4 - 3 18000 2 19000 1 1000 5 - 4 14000 2 19000 2 2500 6 D - 7 6000 4 9000 3 1000 7 E - 6 9000 1 14000 5 1000 8 F - 5 12000 3 14000 2 1000 9 G - 4 3500 2 7500 2 2000 Costs
-Refer to Exhibit 15.5.What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?

(Essay)
4.8/5
(29)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
A B C D E F G H I 1 Activity Description Predecessar Time EST EFT LST LFT Slack 2 A Activity A 4 I 4 I 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E ,F 3 16 19 16 19
-Refer to Exhibit 15.1.What values are placed in cell C5 of the spreadsheet?

(Multiple Choice)
4.8/5
(34)
What is the latest finish time for activity D in the following diagram? 

(Multiple Choice)
4.8/5
(49)
If the following project must be completed by day 18 at minimum cost how do we change the LP model?


(Multiple Choice)
4.8/5
(35)
In project control charts,the horizontal bars are shaded to indicate
(Multiple Choice)
4.8/5
(39)
Which of the following definitions correctly defines the acronym,PERT?
(Multiple Choice)
5.0/5
(31)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set off activities: Activity Predecessor Activities
A ---
B A
C A,B
D A,B
E A,B,C
F A,B,C
G A,B,C,D
H A,B,D
I A,B,C,D,F,G
-Refer to Exhibit 15.6.Is it necessary to draw an arc from the node for activity F to the node for activity I?

(Not Answered)
This question doesn't have any answer yet