An activity

(Multiple Choice)
4.8/5
(38)

Shortening the activity completion time is called

(Multiple Choice)
4.9/5
(38)

Non-critical activities are distinguished by the presence of

(Multiple Choice)
5.0/5
(35)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessor Activities A 1 − B 4 A C 3 B D 3 C E 2 B F 4 E G 2 D,F -Refer to Exhibit 15.4.Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity.What is the critical path for the project and how long should it take to complete it?

(Essay)
4.8/5
(40)

A strength of Gantt charts is that they

(Multiple Choice)
4.9/5
(38)

Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Days Predecessor Activity Required Activities A 5 - B 3 A C 4 A D 7 B, C E 6 C F 5 E G 4 D, F -Refer to Exhibit 15.3.Identify each path through the network and its expected length.

(Essay)
4.7/5
(36)

Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity. A B C D E F G H 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 5 6000 3 8000 2 1000 4 - 3 18000 2 19000 1 1000 5 - 4 14000 2 19000 2 2500 6 D - 7 6000 4 9000 3 1000 7 E - 6 9000 1 14000 5 1000 8 F - 5 12000 3 14000 2 1000 9 G - 4 3500 2 7500 2 2000 Costs  Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.   \begin{array}{|c|c|c|c|c|c|c|c|c|}  \hline& \text { A } & \text { B } & \text { C } & \text { D } & \text { E } & \text { F } & \text { G } & \text { H } \\ \hline 1 & & & \text { Normal } & & \text { Crash } & & \text { Allowable } & \text { Crash Cost } \\ \hline 2 & \text { Activity } & \text { Description } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } & \text { Crash Days } & \text { Per Day } \\\hline 3 & \mathrm{~A} & - & 5 & 6000 & 3 & 8000 & 2 & 1000 \\ \hline 4 & \mathrm{~B} & - & 3 & 18000 & 2 & 19000 & 1 & 1000 \\ \hline 5 & \mathrm{C} & - & 4 & 14000 & 2 & 19000 & 2 & 2500 \\\hline 6 & \text { D } & - & 7 & 6000 & 4 & 9000 & 3 & 1000 \\ \hline 7 & \text { E } & - & 6 & 9000 & 1 & 14000 & 5 & 1000 \\ \hline 8 & \text { F } & - & 5 & 12000 & 3 & 14000 & 2 & 1000 \\ \hline 9 & \text { G } & - & 4 & 3500 & 2 & 7500 & 2 & 2000 \\ \hline&\text { Costs }\\ \hline \end{array}    -Refer to Exhibit 15.5.If the following project must be completed by day 18 at minimum cost how do we change the LP model? -Refer to Exhibit 15.5.If the following project must be completed by day 18 at minimum cost how do we change the LP model?

(Essay)
4.8/5
(27)

Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.  Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     \begin{array} { | c | c | c | c | c | c | c | c | c | c | }  \hline & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } & \text { F } & \text { G } & \text { H } & \text { I } \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessar } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & \text { I } & 4 & \text { I } & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline \text { 6 } & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline8 & \text { G } & \text { Activity G } & \text { E ,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}  -Refer to Exhibit 15.1.What array formula is placed in cell E5 to calculate the Earliest Start Time? A B C D E F G H I 1 Activity Description Predecessar Time EST EFT LST LFT Slack 2 A Activity A 4 I 4 I 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E ,F 3 16 19 16 19 -Refer to Exhibit 15.1.What array formula is placed in cell E5 to calculate the Earliest Start Time?

(Multiple Choice)
4.8/5
(28)

How many paths are there in the following project precedence network? How many paths are there in the following project precedence network?

(Multiple Choice)
4.8/5
(37)

A way to crash an activity is to

(Multiple Choice)
4.8/5
(32)

Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set off activities: Activity Predecessor Activities Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set off activities: Activity Predecessor Activities    A --- B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,F,G -Refer to Exhibit 15.6.Is it necessary to draw an arc from the node for activity A to the node for activity C? A --- B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,F,G -Refer to Exhibit 15.6.Is it necessary to draw an arc from the node for activity A to the node for activity C?

(Essay)
4.9/5
(41)

Activities with zero slack

(Multiple Choice)
4.8/5
(30)

Slack for activity I is computed as

(Multiple Choice)
4.9/5
(31)

What are the immediate successors of activity D in this network? What are the immediate successors of activity D in this network?

(Multiple Choice)
4.8/5
(40)

Critical activities are distinguished by the presence of

(Multiple Choice)
4.9/5
(34)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessor Activities A 1 − B 4 A C 3 B D 3 C E 2 B F 4 E G 2 D,F -Refer to Exhibit 15.4.Identify each path through the network and its expected length.

(Essay)
4.8/5
(33)

Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Days Predecessor Activity Required Activities A 5 - B 3 A C 4 A D 7 B, C E 6 C F 5 E G 4 D, F -Refer to Exhibit 15.3.Draw the CPM network for this problem.Use AON notation.

(Essay)
4.9/5
(37)

Which of the following is true regarding projects?

(Multiple Choice)
4.8/5
(33)

The critical path is the path throughout the network.

(Multiple Choice)
4.8/5
(34)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessor Activities A 1 − B 4 A C 3 B D 3 C E 2 B F 4 E G 2 D,F -Refer to Exhibit 15.4.Draw the CPM network for this problem.Use AON notation.

(Essay)
4.9/5
(40)
Showing 21 - 40 of 65