Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis74 Questions
Exam 2: Introduction to Optimization and Linear Programming73 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet75 Questions
Exam 4: Sensitivity Analysis and the Simplex Method77 Questions
Exam 5: Network Modeling84 Questions
Exam 6: Integer Linear Programming88 Questions
Exam 7: Goal Programming and Multiple Objective Optimization65 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization69 Questions
Exam 9: Regression Analysis82 Questions
Exam 10: Data Mining102 Questions
Exam 11: Time Series Forecasting81 Questions
Exam 12: Introduction to Simulation Using Analytic Solver Platform70 Questions
Exam 13: Queuing Theory87 Questions
Exam 14: Decision Analysis116 Questions
Exam 15: Project Management Online65 Questions
Select questions type
Non-critical activities are distinguished by the presence of
(Multiple Choice)
5.0/5
(35)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity
Days Required
Predecessor Activities
A 1 −
B 4 A
C 3 B
D 3 C
E 2 B
F 4 E
G 2 D,F
-Refer to Exhibit 15.4.Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity.What is the critical path for the project and how long should it take to complete it?
(Essay)
4.8/5
(40)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Days Predecessor Activity Required Activities A 5 - B 3 A C 4 A D 7 B, C E 6 C F 5 E G 4 D, F
-Refer to Exhibit 15.3.Identify each path through the network and its expected length.
(Essay)
4.7/5
(36)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it.They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
A B C D E F G H 1 Normal Crash Allowable Crash Cost 2 Activity Description Time Cost Time Cost Crash Days Per Day 3 - 5 6000 3 8000 2 1000 4 - 3 18000 2 19000 1 1000 5 - 4 14000 2 19000 2 2500 6 D - 7 6000 4 9000 3 1000 7 E - 6 9000 1 14000 5 1000 8 F - 5 12000 3 14000 2 1000 9 G - 4 3500 2 7500 2 2000 Costs
-Refer to Exhibit 15.5.If the following project must be completed by day 18 at minimum cost how do we change the LP model?

(Essay)
4.8/5
(27)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
A B C D E F G H I 1 Activity Description Predecessar Time EST EFT LST LFT Slack 2 A Activity A 4 I 4 I 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E ,F 3 16 19 16 19
-Refer to Exhibit 15.1.What array formula is placed in cell E5 to calculate the Earliest Start Time?

(Multiple Choice)
4.8/5
(28)
How many paths are there in the following project precedence network? 

(Multiple Choice)
4.8/5
(37)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set off activities: Activity Predecessor Activities
A ---
B A
C A,B
D A,B
E A,B,C
F A,B,C
G A,B,C,D
H A,B,D
I A,B,C,D,F,G
-Refer to Exhibit 15.6.Is it necessary to draw an arc from the node for activity A to the node for activity C?

(Essay)
4.9/5
(41)
What are the immediate successors of activity D in this network? 

(Multiple Choice)
4.8/5
(40)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity
Days Required
Predecessor Activities
A 1 −
B 4 A
C 3 B
D 3 C
E 2 B
F 4 E
G 2 D,F
-Refer to Exhibit 15.4.Identify each path through the network and its expected length.
(Essay)
4.8/5
(33)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Days Predecessor Activity Required Activities A 5 - B 3 A C 4 A D 7 B, C E 6 C F 5 E G 4 D, F
-Refer to Exhibit 15.3.Draw the CPM network for this problem.Use AON notation.
(Essay)
4.9/5
(37)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity
Days Required
Predecessor Activities
A 1 −
B 4 A
C 3 B
D 3 C
E 2 B
F 4 E
G 2 D,F
-Refer to Exhibit 15.4.Draw the CPM network for this problem.Use AON notation.
(Essay)