Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Earned value management jointly considers the impact of:
Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
C
Positive variance on an S-curve represents significant project progress.
Free
(True/False)
4.9/5
(38)
Correct Answer:
False
The critical success factor that relates to the underlying purpose for the project is the:
(Multiple Choice)
4.7/5
(35)
Once an activity is begun,it is assumed to be half done under the:
(Multiple Choice)
5.0/5
(35)
Use the earned value table for Project Makeready to determine the earned value at week 49. 

(Multiple Choice)
4.9/5
(42)
In the formation stage,failed projects are more likely to have:
(Multiple Choice)
4.7/5
(34)
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the BEST statement. 

(Multiple Choice)
4.8/5
(38)
Inspired by his trip to Greece,the gentleman farmer decided he needed a Mykonos-style windmill pumping a pond for his sheep and orchard.His earned value table for the project appears below.Develop a plot that shows the project baseline and earned value through June and comment on the project. 

(Essay)
4.8/5
(35)
Take the factors considered by earned value analysis and subtract those considered by project S-curves.The factor(s)you have remaining are:
(Multiple Choice)
4.8/5
(38)
Your organization is in the midst of a project in uncharted waters; nothing you have attempted before comes close to many of the activities that are necessary to bring this project to completion.Your earned value management should probably be tracked closely with a percentage complete rule in increments of 5 to 10 percent.
(True/False)
4.8/5
(34)
Use the earned value table for Project Makeready to calculate their schedule performance index. 

(Multiple Choice)
4.7/5
(26)
The classic S-curve is a plot of cumulative cost versus elapsed time in weeks.
(True/False)
4.7/5
(30)
Use the earned value table to determine the estimated cost to completion given the indicated state of the project. 

(Multiple Choice)
4.9/5
(39)
At the end of week 20,this project has cost $79,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars.
(Multiple Choice)
4.8/5
(34)
The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.
(True/False)
4.9/5
(41)
A project manager needs the work breakdown structure and a time-phased project budget to establish the project baseline.
(True/False)
4.9/5
(36)
It is possible to measure both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
(True/False)
4.8/5
(41)
Showing 1 - 20 of 104
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)