Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
What is the float start time for Activity C given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 - B 7 A C 5 A D 7 B, C
Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
B
In order to reduce the length of a project,it would be wise to shorten:
Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
D
One approach to reducing project length would be to:
Free
(Multiple Choice)
4.7/5
(29)
Correct Answer:
D
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity? Time Predecessor 7 8 13 8 7 6 6 11 12 14 ,,
(Multiple Choice)
4.7/5
(35)
At a burst point in a backward pass,the largest succeeding late start becomes the late finish for that node.
(True/False)
4.9/5
(32)
One of the defining points of a network,a junction point joined to some or all of the others by dependency lines,is called a(n):
(Multiple Choice)
4.8/5
(39)
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity).Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project? Activity Length Predecessor 10 - 18 14 20 ,
(Multiple Choice)
4.9/5
(41)
Discuss any five approaches to reducing the critical path.Which is the most effective and which is the most difficult to achieve? Why?
(Essay)
4.8/5
(35)
What is the late start time for Activity E given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 - B 7 - 8 A 7 A E 4 B F 8 C, D G 9 E, F 7
(Multiple Choice)
4.9/5
(32)
Negative float exists when a project's critical path has been completed more quickly than anticipated.
(True/False)
4.9/5
(38)
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project? Time Predecessor 7 8 13 8 7 6 6 11 12 14 ,,
(Multiple Choice)
4.8/5
(30)
You must know the mean of an activity in order to determine its standard deviation.
(True/False)
4.7/5
(37)
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 - B 7 - D 8 A D 7 A E 4 B F 8 C, D G 9 E, F H 7 G
(Multiple Choice)
4.7/5
(35)
Construct a network using the information in the table and identify the critical path.
Activity Time Predecessor A 4 B 6 A D 9 A D 11 B E 16 B, C F 4 D G 8 E, F H 7 G
(Essay)
4.7/5
(35)
Use the information in the table to determine the early finish time for Activity D. 

(Multiple Choice)
4.8/5
(32)
Use the information in the table to determine the late finish time for Activity B. 

(Multiple Choice)
4.9/5
(45)