Exam 13: Project Evaluation and Control

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A measurement process that determines the project goals and then the degree to which the actual performance lives up to these goals is:

(Multiple Choice)
4.8/5
(43)

The Project Implementation Profile includes this critical success factor.

(Multiple Choice)
4.9/5
(40)

The one factor that earned value management considers that an S-curve does not include is performance.

(True/False)
4.9/5
(34)

The earned value to date divided by the planned value of work scheduled to be performed is the:

(Multiple Choice)
4.8/5
(30)

If an activity's progress is defined as 0% until the activity is complete,the project manager is using:

(Multiple Choice)
4.9/5
(35)

Project goal setting includes setting a baseline plan,which is predicated on:

(Multiple Choice)
4.9/5
(30)

Funding problems are a key success inhibitor in the:

(Multiple Choice)
4.8/5
(37)

Sketch the project control cycle and discuss the activities that take place in each step.

(Essay)
4.8/5
(29)

If significant deviations from the project plan are detected,corrective action is taken and then:

(Multiple Choice)
4.9/5
(33)

Use the information in the table regarding this seven-month project to create two plots.The first plot should be the S-curve for Earned Value.Indicate on this plot whether the project is ahead or behind schedule and by how much.The second plot should be the Earned Schedule and the Estimate at Completion for Time.Comment on the symmetry of this graph and whether you would expect a similar plot from any other project to exhibit similar characteristics.  Month 1 Month 2 Month 3 Month 4  Month 5 Month 6 Month 7 PV ($) $125$275$500$875$1,485$2,325$2,670EV($)$140$280$480$800$1,280$1,975$2,950\begin{array}{|l|l|l|l|l|l|l|l} & \text { Month } 1 & \text { Month } 2 & \text { Month } 3 & \text { Month 4 } & \text { Month } 5 & \text { Month } 6 & \text { Month } 7 \\\hline \text { PV (\$) } & \$ 125 & \$ 275 & \$ 500 & \$ 875 & \$ 1,485 & \$ 2,325 & \$ 2,670 \\\hline \mathbb{E V}(\$) & \$ 140 & \$ 280 & \$ 480 & \$ 800 & \$ 1,280 & \$ 1,975 & \$ 2,950 \\\hline\end{array}

(Essay)
4.9/5
(48)

Use this earned schedule table to determine the schedule variance ($)for this project at the end of Month 6.  Month 1 Month 2  Month 3  Month 4  Month 5 Month 6  Month 7PV($)$125$275$500$875$1,485$2,325$2,670EV($)$50$120$255$420$715$865$0\begin{array}{l|l|l|l|l|l|l|l} & \text { Month } 1 & \text { Month 2 } & \text { Month 3 } & \text { Month 4 } & \text { Month } 5 & \text { Month 6 } & \text { Month } 7 \\\hline \mathrm{PV}(\$) & \$ 125 & \$ 275 & \$ 500 & \$ 875 & \$ 1,485 & \$ 2,325 & \$ 2,670 \\\hline \mathrm{EV}(\$) & \$ 50 & \$ 120 & \$ 255 & \$ 420 & \$ 715 & \$ 865 & \$ 0\end{array}

(Multiple Choice)
4.9/5
(30)

What is earned value management and how can it be used to monitor project status?

(Essay)
4.8/5
(38)

What are the inputs and the steps in applying earned value management as a project management tool?

(Essay)
4.8/5
(27)

What is a tracking Gantt chart and what are the benefits and drawbacks of its use?

(Essay)
4.8/5
(42)

The first step in earned value management is to:

(Multiple Choice)
4.8/5
(35)

Inspired by his trip to Greece,the gentleman farmer decided he needed a Mykonos-style windmill pumping a pond for his sheep and orchard.His earned value table for the project appears below.At the end of June,what was the estimated time to completion and the estimated cumulative cost to completion? Inspired by his trip to Greece,the gentleman farmer decided he needed a Mykonos-style windmill pumping a pond for his sheep and orchard.His earned value table for the project appears below.At the end of June,what was the estimated time to completion and the estimated cumulative cost to completion?

(Essay)
4.9/5
(38)

At the end of week 10,this project has cost $9,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars. Duration (weeks) 5 10 15 20 25 \% Comp Conceptual Design 10 6 100\% Graphics Design 12 6 4 30\% Copyright 4 5 6 0\% Samples 4 2 0\% Tooling 6 9 4 0\% Production 10 18 2 6 14 0\% Total 10 28 50 76 100 Cumulative 22 26 24

(Multiple Choice)
4.8/5
(38)

A tracking Gantt chart:

(Multiple Choice)
4.9/5
(44)

Since a project may get ahead of or fall behind schedule,a calendar date cannot be a milestone.

(True/False)
4.9/5
(40)

A project manager that uses milestones as a project control device is using a:

(Multiple Choice)
4.8/5
(40)
Showing 41 - 60 of 104
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)