Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
What is the total amount budgeted for design costs in this time-phased budget? Activity January February March April Survey 8,000 Design 5,250 4,500 Dirt 6,700 Foundation 12,550 Framing 37,250 Plumb 7,800 Wire 5,500
Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
C
There is a tendency for different departments or functions to compete for scarce resources in a zero-sum game when bottom-up budgeting is used to develop a project budget.
Free
(True/False)
4.8/5
(32)
Correct Answer:
False
There was no way that the study tour to Italy could cost only $1500 for 14 days and 13 nights and include all transportation,meals and hotels,but the smarmy professor knew that students would balk at a higher advertised price.Once they were thousands of miles away from home in a country where none of them spoke the language it would be easier to tell them about unanticipated charges and approach the more realistic price of $3500 per person.This type of:
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
C
An activity with a learning rate of 0.8 takes 30 hours for the first six units.How long will it take to complete this task for the 12th time?
(Multiple Choice)
4.9/5
(37)
If it takes 40 hours to complete the first unit and the company knows from experience that the learning rate should be 0.75,how fast can they be expected to finish all ten units?
(Multiple Choice)
4.7/5
(44)
The new bridge would require 14 piers to support it and it was known that each time a pier is sunk into the harbor it would take 30 man hours of labor at $50 per hour.An activity-based costing of the entire pier system results in a total labor cost of:
(Multiple Choice)
4.9/5
(35)
The new artisanal greenhouse would require 700 empty wine bottles be embedded in a frame made of clay and straw.The builder,a man with too much time on his hands,had determined that each time a bottle was added to the structure it would take 30 minutes of labor at $7.50 per hour in the blazing sun.An activity-based costing of the entire artisanal greenhouse revealed that the total labor cost would be:
(Multiple Choice)
4.8/5
(37)
A budget containing disaggregated figures across the schedule when work is planned is a:
(Multiple Choice)
4.9/5
(31)
An expedited cost is one that does not vary with respect to their usage.
(True/False)
4.9/5
(31)
An allocation of extra funds to cover uncertainties and improve chances that the project can be completed within the timeframe originally specified is a:
(Multiple Choice)
4.7/5
(38)
Material is an example of a cost that is recurring,variable and direct.
(True/False)
4.9/5
(32)
Provide examples and discuss the differences between direct and indirect costs.
(Essay)
4.8/5
(46)
A learning rate of 90% means that for every doubling of output,the time required by the activity falls by 10%.
(True/False)
4.9/5
(43)
A contingency rate of 10% on a building project budgeted at $20 million means the project organization is hoping to bring the project in for around:
(Multiple Choice)
4.9/5
(31)
A time-phased budget allocates costs across both project activities and the anticipated time in which the budget is to be expended.
(True/False)
4.9/5
(38)
Showing 1 - 20 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)