Exam 12: Resource Management
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Create a resource loading chart for the project described by this table and then adjust activities by splitting them or delaying them in order to meet the resource constraints of 8 hours of work per day.Show your new resource loading chart,indicating which activities have been adjusted.What is the change in project completion dates?


Free
(Essay)
4.9/5
(35)
Correct Answer:
The initial resource loading chart is below; project completion time is 20 days but the combination of activities R and G and activities M and D exceed the 8-hour-per-day threshold.
Activities R and M both have 5 days of slack; if activity R is delayed until day 5,it will begin then and be completed on day 8.M must be delayed until D is completed,which will then delay the project's completion by 4 days.
Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project. Activity Duration Predecessor 5 days - 4 days 5 days A 6 days 6 days , 6 days
Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
A
The best method for establishing the existence of resource conflicts across project activities uses resource-loading charts.
Free
(True/False)
4.9/5
(35)
Correct Answer:
True
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed. Activity Time Predecessor A 2 B 3 A C 6 B 5 A E 3 C F 2 D G 2 E,F
(Essay)
4.9/5
(34)
Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. Activity Duration Predecessor 5 days - 4 days 5 days A 6 days 6 days , 6 days
(Multiple Choice)
4.7/5
(24)
A resource loading form can be generated once you have developed:
(Multiple Choice)
4.9/5
(36)
The independent axis of a resource loading chart is in units of:
(Multiple Choice)
4.7/5
(31)
Use the resource loading table to determine which of the Yaki sisters is over-allocated. Resource Work Details 23- Oct 30- Oct Suki 64 Work 32 32 16 Work 16 24 Work 16 8 D 24 Work 24 Terri 40 Work 16 16 8 24 Work 16 8 E 16 Work 8 8
(Multiple Choice)
4.9/5
(39)
Placing resources on a detailed schedule of tasks is referred to as:
(Multiple Choice)
4.8/5
(27)
In general,when constructing a resource loading chart,one should avoid:
(Multiple Choice)
4.9/5
(37)
The One Shovel Construction Company is hired by the City of Edmond to lay sewer pipe from the east end of town to the west end of town using their single shovel to dig the trench.While the crew would like to begin at both ends simultaneously and have a dramatic ceremony when both ends meet,they find themselves with a bit of a:
(Multiple Choice)
4.7/5
(38)
A project is composed of the seven activities shown in the table where all activities are in weeks.
The resource profile for an early start schedule is plotted below.
Suppose that the line representing resource usage is a function of time and is described by the equation Usage=f(t).What is the definite integral of this function over the domain 0 to 52? In other words,find the solution to: for this project.


(Essay)
4.7/5
(39)
The BEST method for establishing the existence of resource conflicts across project activities uses:
(Multiple Choice)
4.9/5
(36)
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The First in Line rule would begin work with project: Resource Resource Resource Project Date Rec'd Date Due 1 2 3 A Apr 2006 Oct 2006 125 200 100 B Feb 2006 Sep 2006 200 350 400 C Mar 2006 Alg 2006 100 650 200 Tan 2006 Nov 2006 150 250 350
(Multiple Choice)
4.8/5
(29)
Which of the following would NOT typically be displayed in a resource loading table?
(Multiple Choice)
4.7/5
(36)
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack? Activity Duration Predecessor WBS ID W 4 - 12 A 3 W 16 B 4 W 15 C 5 W 13 D 6 W 14 E 1 B 17 Z 7 A, E, C, D 18
(Multiple Choice)
4.8/5
(37)
Rank the three key parameters,schedule slippage,resource utilization,and in-process inventory,from most critical to least critical for an organization and justify your ranking.
(Essay)
4.9/5
(29)
Consider the project that is neatly summarized in this table.What are the highest priority activities when using the most resources required leveling heuristic? Activity Duration Predecessors Workers Required A 8 - 3 B 2 - 4 D 6 A 5 E 7 B 6
(Multiple Choice)
4.9/5
(30)
A resource loading table is created through identifying the project activities and the resources required for completion and applying this information to the project schedule baseline.
(True/False)