Exam 8: Facility and Work Design
Exam 1: Goods, Services, and Operations Management65 Questions
Exam 2: Value Chains68 Questions
Exam 3: Measuring Performance in Operations80 Questions
Exam 4: Operations Strategy65 Questions
Exam 5: Technology and Operations Management72 Questions
Exam 6: Goods and Service Design92 Questions
Exam 7: Process Selection, Design, and Analysis88 Questions
Exam 8: Facility and Work Design79 Questions
Exam 9: Supply Chain Design71 Questions
Exam 10: Capacity Management70 Questions
Exam 11: Forecasting and Demand Planning76 Questions
Exam 12: Managing Inventories89 Questions
Exam 13: Resource Management88 Questions
Exam 14: Operations Scheduling and Sequencing66 Questions
Exam 15: Quality Management73 Questions
Exam 16: Quality Control and Spc86 Questions
Exam 17: Lean Operating Systems63 Questions
Exam 18: Project Management65 Questions
Exam 19: Work Measurement, Learning Curves, and Standards56 Questions
Exam 20: Queuing Analysis39 Questions
Exam 21: Modeling Using Linear Programming43 Questions
Exam 22: Simulation39 Questions
Exam 23: Work Measurement, Learning Curves, and Standards44 Questions
Select questions type
Cycle time should be smaller than the largest operation time.
Free
(True/False)
4.9/5
(30)
Correct Answer:
False
The determination of specific job tasks and responsibilities is called ____.
Free
(Multiple Choice)
4.7/5
(36)
Correct Answer:
A
____ set their own goals and inspect their own work, often hire their own replacements and prepare their own budgets.
Free
(Multiple Choice)
5.0/5
(34)
Correct Answer:
D
Services such as legal and medical specialties employ cellular-type layouts as do manufacturers.
(True/False)
4.8/5
(34)
CRAFT is a process layout technique that tries to improve on a current solution by exchanging two or three departments at a time to determine if total materials handling costs have been reduced.
(True/False)
4.9/5
(27)
Product layouts offer higher flexibility with low productivity and process layouts have limited flexibility with high productivity.
(True/False)
4.8/5
(37)
For the following assembly line data, balance the line for an output of 30 units in a 7.5 hour shift. Use the "longest task time first" rule.
Task Time in minutes) Predecessors A 8 none B 1 none C 2 none D 3 A, B E 3 B, C F 2 D G 9 E H 6 E I 7 F, G J 1 H K I, J Total 45
(Essay)
4.7/5
(35)
The nine tasks necessary to assemble a vacuum cleaner are listed below. The time to perform each task and the tasks that must immediately precede are also listed. 300 vacuums are needed per hour and 50 minutes per hour are productive.
Task Thime in minutes) Predecessars A .15 none B .06 A C .05 B D .12 B E .09 B F .16 B G .08 C,D,E H .06 G,F I .05
a. Compute the cycle time per unit in minutes.
b. Compute the minimum number of workstations required.
c. Use the longest-task-time heuristic to balance the production line.
d. Compute the efficiency of the assembly line.
(Essay)
4.9/5
(33)
An) ____ performs entire jobs rather than specialized, assembly line work.
(Multiple Choice)
4.7/5
(32)
For a given cycle time in line balancing, assembly-line efficiency can be increased by
(Multiple Choice)
4.9/5
(28)
ALDEP is a process layout technique that focuses on materials handling costs as the primary solution.
(True/False)
4.9/5
(37)
In your first job you must set up an assembly line to assemble a computer mouse. The precedence diagram below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast output rate) is 60 units per shift.
a. Compute the cycle time per unit in minutes.
b. Compute the minimum number of workstations required.
c. Use the longest-task-time heuristic to balance the assembly line.
d. Compute the efficiency of your assembly line.

(Essay)
4.7/5
(33)
A small electronics company assembles power supplies for use in computers, printers and Fax machines. They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the longest-task-time heuristic. The demand for power supplies is 70 per hour, and the productive time per hour is 52 minutes. The following table provides details on their operation.
Task Time in minutes) Predecessors A .54 none B .34 C .11 .09 .43 , .22 .62 .35 , .21 .57 .33 ,
a. What is the cycle time?
b. What is the theoretical minimum number of workstations?
c. What tasks go into the first workstation?
d. How many workstations are needed for the entire line?
e. What is the assembly-line efficiency?
(Essay)
4.7/5
(40)
Differentiate among product layout, process layout, cellular layout, and fixed-position layout. State the advantages and disadvantages of each.
(Essay)
4.7/5
(29)
All of the following are common objectives of layout studies except
(Multiple Choice)
4.8/5
(34)
The production of large goods such as airplanes is best accomplished using a ____ layout.
(Multiple Choice)
4.8/5
(32)
____ classifies parts into families so that cellular layouts can be effectively used.
(Multiple Choice)
4.7/5
(40)
Showing 1 - 20 of 79
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)