Exam 14: Operations Scheduling and Sequencing
Exam 1: Goods, Services, and Operations Management65 Questions
Exam 2: Value Chains68 Questions
Exam 3: Measuring Performance in Operations80 Questions
Exam 4: Operations Strategy65 Questions
Exam 5: Technology and Operations Management72 Questions
Exam 6: Goods and Service Design92 Questions
Exam 7: Process Selection, Design, and Analysis88 Questions
Exam 8: Facility and Work Design79 Questions
Exam 9: Supply Chain Design71 Questions
Exam 10: Capacity Management70 Questions
Exam 11: Forecasting and Demand Planning76 Questions
Exam 12: Managing Inventories89 Questions
Exam 13: Resource Management88 Questions
Exam 14: Operations Scheduling and Sequencing66 Questions
Exam 15: Quality Management73 Questions
Exam 16: Quality Control and Spc86 Questions
Exam 17: Lean Operating Systems63 Questions
Exam 18: Project Management65 Questions
Exam 19: Work Measurement, Learning Curves, and Standards56 Questions
Exam 20: Queuing Analysis39 Questions
Exam 21: Modeling Using Linear Programming43 Questions
Exam 22: Simulation39 Questions
Exam 23: Work Measurement, Learning Curves, and Standards44 Questions
Select questions type
Scheduling problems occur almost exclusively in manufacturing.
Free
(True/False)
4.8/5
(34)
Correct Answer:
False
When several products share common facilities, product sequencing affects cost.
Free
(True/False)
4.8/5
(38)
Correct Answer:
True
Explain why any sequence chosen in the single-machine scheduling problem will not change makespan time.
Free
(Essay)
4.8/5
(36)
Correct Answer:
The total processing time for all jobs is constant; it is simply the sum of the individual processing times, which is sequence independent. M = C - S where
M = makespan of a group of jobs
C = completion time of last job in the group
S = start time of first job in the group
so it doesn't change.
A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States. They are job shops that handle a variety of outpatient surgical procedures. Their process is set up so that one doctor cuts and the other sews. They have five patients to sequence for tomorrow. Since the weather forecast is for a cool and sunny day, they would also like to play golf tomorrow. They want to sequence their patients with the objective of minimizing the time from the beginning of the first job until the finish of that job. The patients and estimated times are as follows:
Patent Cut Time hours) Sew Time hours) A 2.3 2.8 B 2.5 3.0 C 2.0 1.5 D 0.6 1.0 E 3.6 2.6
Sequence the patients using Johnson's Method, state the schedule for each operation, and determine the minimum makespan.
(Essay)
4.8/5
(37)
In practice, whenever processing times of a set of jobs are about equal, managers typically use a first-come, first-serve rule.
(True/False)
4.9/5
(41)
Since all jobs eventually get done, job sequencing has no effect on resource utilization.
(True/False)
5.0/5
(37)
For a single processor, a first-come, first-served FCFS) rule minimizes the average flow time because customer waiting time will be minimized.
(True/False)
4.8/5
(27)
Sequencing is not as much of a concern when several activities use a common resource.
(True/False)
4.7/5
(35)
A movie theater requires the following minimum number of employees, each of which is required to have two consecutive days off.
Day: M Tu W Th F Sa Su Mirimum Persunel Required: 1 1 3 2 5 4 3
How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.
(Essay)
4.8/5
(32)
The EDD rule minimizes the maximum of jobs past due but doesn't perform well on average flow-time, WIP inventory or resource utilization.
(True/False)
4.9/5
(38)
The following five jobs, along with their processing time and due dates, are given below.
Processing Days Due Jab Time days) Fram Today A 8 12 B 4 9 C 3 6 D 7 7 E 5 20
a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs
b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.
(Essay)
5.0/5
(36)
Gantt charts can show what jobs are ahead of schedule, behind schedule, and on schedule.
(True/False)
4.8/5
(35)
Short-term capacity fluctuations necessitate changes in schedules. List at least five factors affecting short-term capacity.
(Essay)
4.8/5
(42)
Which of the following is an example of a situation for which a Gantt chart would be appropriate?
(Multiple Choice)
4.9/5
(30)
Flow time is the amount of time a job spends in a shop or factory.
(True/False)
4.9/5
(38)
The table below includes processing times and due dates for five jobs.
Processing Days Due Job Time days) Fram Today A 16 24 B 23 30 C 22 40 D 8 28 E 10 18
a. Use the Shortest Processing Time Rule (SPT) to determine the average flow time.
b. Use the Earliest Due Date Rule (EDD) to determine the average lateness.
(Essay)
5.0/5
(36)
Showing 1 - 20 of 66
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)