The project manager will conduct one or more kickoff meetings to develop plans for establishing the project office.

Free
(True/False)
4.8/5
(37)
Correct Answer:
Verified

True

Determining the policies that are needed for the smooth execution of a project relates to which of the following agenda items of alignment sessions?

Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
Verified

E

Which of the following statements is true regarding the start-up phase?

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
Verified

D

A well-developed project scope statement provides the project team with information the team needs to design and execute the project plan.

(True/False)
4.7/5
(37)

The _____ matrix is a table that displays the responsibilities and distribution for each type of document.

(Multiple Choice)
4.8/5
(40)

The _____ of an organization is a statement of why it exists.

(Multiple Choice)
4.9/5
(32)

Which of the following is NOT true about document control?

(Multiple Choice)
4.9/5
(28)

Role clarity is critical to the planning and execution of a project.

(True/False)
4.7/5
(41)

An) _____ is an end toward which effort is directed that has a measurable outcome.

(Multiple Choice)
4.8/5
(28)

_____ conventions for files and the versions of files should be consistent with the practices of the parent organization or with the client organization so that the files may be archived with files from other projects.

(Short Answer)
4.7/5
(35)

The role clarification process enables the team to develop _____ processes, where two or more members share similar roles or responsibilities.

(Short Answer)
4.8/5
(41)

It is important to accomplish alignment among key stakeholders during the _____ phase itself.

(Multiple Choice)
4.8/5
(32)

One of the necessary components of a change documentation process is to estimate the time needed to evaluate the change.

(True/False)
4.8/5
(42)

Typically, the client will develop the first draft of the project scope.

(True/False)
4.9/5
(38)

What are some of the common agenda items in alignment sessions?

(Essay)
4.7/5
(37)

_____ means labeling each document revision to enable the team to understand the latest activity and status of the document.

(Multiple Choice)
4.8/5
(31)

_____ are those persons in the organization who know how to generate or find information.

(Multiple Choice)
4.7/5
(30)

As long as the end date of a project or major objectives are not delayed, a formal change request to the client is not needed.

(True/False)
4.9/5
(32)

A not-for-profit organization must consider the cost of each project and how much profit it is likely to generate.

(True/False)
4.9/5
(38)

The time period it takes to recoup the original expense without considering interest payments or other complicating factors is called _____.

(Multiple Choice)
4.7/5
(31)