Exam 9: Estimating and Managing Costs
Exam 1: Introduction to Project Management86 Questions
Exam 2: Project Profiling68 Questions
Exam 3: Project Phases and Organization80 Questions
Exam 4: Understanding and Meeting Client Expectations59 Questions
Exam 5: Working With People on Projects71 Questions
Exam 6: Communication Technologies71 Questions
Exam 7: Starting a Project74 Questions
Exam 8: Project Time Management73 Questions
Exam 9: Estimating and Managing Costs65 Questions
Exam 10: Managing Project Quality70 Questions
Exam 11: Managing Project Risk65 Questions
Exam 12: Project Procurement and Closure70 Questions
Select questions type
_____ is the sum of budgeted expenses up to a particular point in the schedule.
Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
B
Estimate to complete equals budget at completion minus schedule variance, i.e., ETC = BAC − SV.
Free
(True/False)
4.8/5
(37)
Correct Answer:
False
_____ is the sum of money spent so far.
Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
D
The money needed to pay for a project is usually transferred to the project account shortly before it is needed.
(True/False)
4.9/5
(33)
The process of subtotaling costs by category or activity is called _____.
(Multiple Choice)
4.9/5
(26)
A positive cost variance CV) indicates that the project is _____.
(Multiple Choice)
4.9/5
(41)
_____ is the difference between the earned value and the planned value.
(Multiple Choice)
4.8/5
(37)
Reconsidering the selection of the project should take into consideration the _____ of the competing projects that were not chosen and who the _____ are for the projects that would be affected.
(Multiple Choice)
4.8/5
(41)
_____ is money that is available for changing the scope of the project.
(Multiple Choice)
4.7/5
(41)
On projects with low complexity, the cost estimates can be done on spreadsheet software.
(True/False)
4.9/5
(32)
The methods used to estimate the cost of a project during the selection phase are generally slower and consume more resources than those used to create detailed estimates in later phases.
(True/False)
4.9/5
(37)
Which is the most accurate and time-consuming estimating method? Explain.
(Essay)
4.9/5
(29)
The term _____ refers to the budgeted cost of work scheduled that has been done.
(Short Answer)
4.9/5
(29)
The process of matching funds provided with funds spent is called _____.
(Multiple Choice)
4.8/5
(35)
Unlike management reserves, contingency reserves are not likely to be spent and are not part of the project's budget baseline, but they can be included in the total project budget.
(True/False)
4.8/5
(31)
_____ is the money held to pay for predictable but unspecified extra costs.
(Multiple Choice)
4.8/5
(33)
Measures such as percentage of activities completed or percentage of measurement units completed are adequate for high complexity projects.
(True/False)
4.7/5
(38)
If the money needed to pay for a project is transferred to the project too far in advance:
(Multiple Choice)
4.7/5
(31)
The detailed cost estimates for each activity in the project is the actual cost of work performed.
(True/False)
4.9/5
(30)
Showing 1 - 20 of 65
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)