The relationship between a predecessor activity and a successor activity is called an) _____.

Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
Verified

C

When the scope of the project is being determined, a _____ schedule that shows the major tasks and approximate start and end dates is developed to allow senior management to make decisions about the scope of the project stockholders.

Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
Verified

C

Resource calendars must be considered in the backward pass as well as the forward pass.

Free
(True/False)
4.9/5
(34)
Correct Answer:
Verified

True

A project that has completed 25 percent of the scheduled activities indicates that the project is 25 percent complete.

(True/False)
4.8/5
(37)

Describe the steps to calculate late start dates.

(Essay)
4.9/5
(37)

Activities that have predecessor-successor relationships occur concurrently.

(True/False)
4.9/5
(42)

Which of the following is NOT true about a master schedule?

(Multiple Choice)
4.7/5
(40)

The project work breakdown structure WBS):

(Multiple Choice)
4.9/5
(31)

Compare and contrast lag and lead times.

(Essay)
4.8/5
(33)

The time an activity that is not on the critical path can be delayed without delaying the start of a successor activity is called _____.

(Multiple Choice)
4.8/5
(30)

Which of the following is a basic feature of project scheduling software?

(Multiple Choice)
4.7/5
(25)

The master schedule is rarely part of a project contract.

(True/False)
4.7/5
(40)

_____ is the difference between the finish date of the last activity on the critical path and the project completion date.

(Multiple Choice)
4.7/5
(44)

The graphical representation of the sequencing of project activities is called an) _____.

(Short Answer)
5.0/5
(35)

A common resource constraint is availability.

(True/False)
4.8/5
(34)

Distributing the work load to reduce uneven concentrations of work is called _____.

(Multiple Choice)
4.9/5
(32)

You cannot miss an important constraint if you apply the resource calendar to each activity to make sure the people and equipment are available on those dates.

(True/False)
4.8/5
(35)

Resource calendars become important tools when:

(Multiple Choice)
4.8/5
(34)

The unit of time used to develop the activity duration is a function of:

(Multiple Choice)
4.7/5
(34)

If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount.

(True/False)
4.7/5
(21)