Exam 8: Managing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Table 3.4 Table 3.4    -Using Table 3.4,what is the latest finish time for activity D? -Using Table 3.4,what is the latest finish time for activity D?

Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
Verified

C

A precedence relationship specifies that one activity cannot start until a preceding activity has been started.

Free
(True/False)
4.9/5
(29)
Correct Answer:
Verified

False

The earliest start time (ES)for an activity is the maximum of the earliest finish (EF)times for all the activities that immediately precede the activity.

Free
(True/False)
4.8/5
(43)
Correct Answer:
Verified

True

Identify and briefly explain the four categories of project risks.

(Essay)
4.7/5
(40)

The ________ cost refers to the additional cost associated with reducing an activity time in a project network.

(Essay)
4.7/5
(37)

Free slack is the amount of time that an activity's earliest finish time can be delayed without delaying the earliest start time of any activity immediately following it.

(True/False)
4.8/5
(35)

Assume that activity G has the following times: Early start time = 7 days Early finish time = 13 days Late start time = 15 days Late finish time = 21 days Which of the following statements is TRUE about activity G?

(Multiple Choice)
4.9/5
(28)

Table 3.7 Table 3.7    -Using Table 3.7,what is the latest start time for activity A? -Using Table 3.7,what is the latest start time for activity A?

(Multiple Choice)
4.9/5
(28)

The work breakdown structure is a statement of all work that has to be completed.

(True/False)
4.9/5
(37)

Total slack can be calculated as the difference between the latest start (LS)and earliest start (ES),or by the difference between the latest finish (LF)and earliest finish (EF).

(True/False)
4.8/5
(36)

Table 3.7 Table 3.7    -Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become? -Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?

(Multiple Choice)
4.9/5
(37)

Discuss the importance of establishing the scope,time frame,and resources to be allocated to a project before the project is actually started.

(Essay)
4.8/5
(41)

Network methods let project managers analyze the time and cost implications of resource trade-offs.

(True/False)
4.9/5
(32)

Table 3.8 Table 3.8    -Using Table 3.8,what is the earliest completion time of the project? -Using Table 3.8,what is the earliest completion time of the project?

(Multiple Choice)
4.8/5
(28)

The ________ is the shortest time in which an activity can be completed if all goes exceptional well.

(Essay)
4.9/5
(32)

Table 3.9 All activity times for the project are in weeks. Table 3.9 All activity times for the project are in weeks.    -Using Table 3.9,what is the expected time of completion of the project? -Using Table 3.9,what is the expected time of completion of the project?

(Multiple Choice)
4.9/5
(42)

For controlling projects,the Schedule Performance Index (SPI)equals the cost of the work that was scheduled to have been completed by a particular date based on the original budget and project plan.

(True/False)
4.9/5
(36)

Table 3.3 Table 3.3    -Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date? -Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?

(Multiple Choice)
4.8/5
(33)

Table 3.6 Table 3.6    -Using Table 3.6,what is the slack for activity G? -Using Table 3.6,what is the slack for activity G?

(Multiple Choice)
4.8/5
(31)

The earliest start time for an activity is equal to the

(Multiple Choice)
4.9/5
(36)
Showing 1 - 20 of 152