Exam 8: Managing Projects
Exam 1: Creating Customer Value Through Operations92 Questions
Exam 2: Supply Chain Management100 Questions
Exam 3: Process Configuration114 Questions
Exam 4: Capacity101 Questions
Exam 5: Inventory Management152 Questions
Exam 6: Quality and Process Improvement197 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects152 Questions
Exam 9: Location and Layout197 Questions
Exam 10: Managing Demand and Forecasting139 Questions
Exam 11: Operations Planning and Scheduling123 Questions
Exam 12: Resource Planning151 Questions
Exam 13: Waiting Lines93 Questions
Exam 14: Decision Making73 Questions
Exam 15: Financial Analysis41 Questions
Exam 16: Work Measurement97 Questions
Exam 17: Learning Curve Analysis44 Questions
Exam 18: Computer-Integrated Manufacturing53 Questions
Exam 19: Acceptance Sampling Plans71 Questions
Exam 20: Simulation36 Questions
Exam 21: Special Inventory Models32 Questions
Exam 22: Linear Programming47 Questions
Select questions type
Table 3.4
-Using Table 3.4,what is the latest finish time for activity D?

Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
C
A precedence relationship specifies that one activity cannot start until a preceding activity has been started.
Free
(True/False)
4.9/5
(29)
Correct Answer:
False
The earliest start time (ES)for an activity is the maximum of the earliest finish (EF)times for all the activities that immediately precede the activity.
Free
(True/False)
4.8/5
(43)
Correct Answer:
True
The ________ cost refers to the additional cost associated with reducing an activity time in a project network.
(Essay)
4.7/5
(37)
Free slack is the amount of time that an activity's earliest finish time can be delayed without delaying the earliest start time of any activity immediately following it.
(True/False)
4.8/5
(35)
Assume that activity G has the following times: Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
(Multiple Choice)
4.9/5
(28)
Table 3.7
-Using Table 3.7,what is the latest start time for activity A?

(Multiple Choice)
4.9/5
(28)
The work breakdown structure is a statement of all work that has to be completed.
(True/False)
4.9/5
(37)
Total slack can be calculated as the difference between the latest start (LS)and earliest start (ES),or by the difference between the latest finish (LF)and earliest finish (EF).
(True/False)
4.8/5
(36)
Table 3.7
-Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?

(Multiple Choice)
4.9/5
(37)
Discuss the importance of establishing the scope,time frame,and resources to be allocated to a project before the project is actually started.
(Essay)
4.8/5
(41)
Network methods let project managers analyze the time and cost implications of resource trade-offs.
(True/False)
4.9/5
(32)
Table 3.8
-Using Table 3.8,what is the earliest completion time of the project?

(Multiple Choice)
4.8/5
(28)
The ________ is the shortest time in which an activity can be completed if all goes exceptional well.
(Essay)
4.9/5
(32)
Table 3.9
All activity times for the project are in weeks.
-Using Table 3.9,what is the expected time of completion of the project?

(Multiple Choice)
4.9/5
(42)
For controlling projects,the Schedule Performance Index (SPI)equals the cost of the work that was scheduled to have been completed by a particular date based on the original budget and project plan.
(True/False)
4.9/5
(36)
Table 3.3
-Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?

(Multiple Choice)
4.8/5
(33)
Table 3.6
-Using Table 3.6,what is the slack for activity G?

(Multiple Choice)
4.8/5
(31)
Showing 1 - 20 of 152