Exam 8: Managing Projects
Exam 1: Creating Customer Value Through Operations92 Questions
Exam 2: Supply Chain Management100 Questions
Exam 3: Process Configuration114 Questions
Exam 4: Capacity101 Questions
Exam 5: Inventory Management152 Questions
Exam 6: Quality and Process Improvement197 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects152 Questions
Exam 9: Location and Layout197 Questions
Exam 10: Managing Demand and Forecasting139 Questions
Exam 11: Operations Planning and Scheduling123 Questions
Exam 12: Resource Planning151 Questions
Exam 13: Waiting Lines93 Questions
Exam 14: Decision Making73 Questions
Exam 15: Financial Analysis41 Questions
Exam 16: Work Measurement97 Questions
Exam 17: Learning Curve Analysis44 Questions
Exam 18: Computer-Integrated Manufacturing53 Questions
Exam 19: Acceptance Sampling Plans71 Questions
Exam 20: Simulation36 Questions
Exam 21: Special Inventory Models32 Questions
Exam 22: Linear Programming47 Questions
Select questions type
Which one of the following best describes the critical path of a PERT/CPM network?
(Multiple Choice)
4.8/5
(45)
In an activity-on-node (AON)network,the nodes represent ________ whereas the arcs represent ________.
(Multiple Choice)
4.8/5
(41)
________ simply adds more of an overloaded resource to maintain the schedule of an activity.
(Essay)
4.9/5
(29)
A project is an interrelated set of activities that has a definite starting and ending point.
(True/False)
4.7/5
(36)
Table 3.3
-Using Table 3.3,what is the minimum number of activities that would have to be crashed in order to cause a decrease in the project's earliest completion date?

(Multiple Choice)
4.8/5
(25)
Table 3.11
You are responsible for managing a project with the
following activities (times are given in days).
-Using,Table 3.11,what is the critical path and expected completion time for this project?

(Multiple Choice)
4.8/5
(34)
Resource allocation is an attempt to shift ________ from activities with slack to those on the critical path where resources are overloaded.
(Essay)
4.8/5
(30)
________ is a measure of the probability and consequence of not reaching a defined project goal.
(Essay)
4.8/5
(41)
Of the four major phases in project life cycles,typically the execution stage requires the most resources.
(True/False)
4.7/5
(29)
Typically activities along the critical path have more slack than activities not on the critical path.
(True/False)
4.8/5
(36)
Table 3.1
Time (weeks)
-Using Table 3.1,which activity will have the largest amount of slack?

(Multiple Choice)
5.0/5
(34)
A critical path is the sequence of activities between a project's start and finish.
(True/False)
4.9/5
(30)
Each activity in the work breakdown structure must have an "owner" who is responsible for doing the work.
(True/False)
4.8/5
(41)
Describe the four steps followed to determine the minimum-cost schedule for a project that is planned based on the critical path method (CPM).
(Essay)
4.8/5
(35)
Table 3.8
-Using Table 3.8,what is the critical path of the above project?

(Multiple Choice)
4.9/5
(30)
Scope creep refers to all activities that have yet to be completed in a project.
(True/False)
4.9/5
(37)
The crash cost is the additional cost associated with reducing the time required to complete an activity in a project.
(True/False)
4.8/5
(44)
Showing 41 - 60 of 152
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)