Exam 8: Managing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following is NOT one of the five steps involved in planning projects?

(Multiple Choice)
4.9/5
(33)

Table 3.11 You are responsible for managing a project with the following activities (times are given in days). Table 3.11 You are responsible for managing a project with the following activities (times are given in days).    -Using,Table 3.11,which of the following activities has the largest amount of slack? -Using,Table 3.11,which of the following activities has the largest amount of slack?

(Multiple Choice)
4.8/5
(43)

Projects cannot have more than one critical path.

(True/False)
4.8/5
(37)

________ is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.

(Essay)
4.8/5
(44)

Explain how cost-time tradeoffs should be analyzed for projects.

(Essay)
4.8/5
(45)

Which one of the following conditions violates the assumptions of PERT/CPM networks?

(Multiple Choice)
4.7/5
(39)

________ is an attempt to reduce the peaks and valleys in resource needs by shifting the schedules of conflicting activities within their earliest and latest start dates.

(Essay)
4.9/5
(42)

A Gantt chart is a project schedule that superimposes project activities on a time line.

(True/False)
4.9/5
(38)

When using the beta distribution for estimating activity times,

(Multiple Choice)
4.8/5
(35)

To calculate the probability of completing a project by a certain date,

(Multiple Choice)
4.8/5
(39)

Table 3.2 Time (days) Table 3.2 Time (days)    -Using Table 3.2,what is the earliest expected time of completion of the whole project? -Using Table 3.2,what is the earliest expected time of completion of the whole project?

(Multiple Choice)
4.7/5
(31)

Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks). Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks).    -Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question. -Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.

(Multiple Choice)
4.9/5
(32)

A(n)________ chart is a project schedule that superimposes project activities,with their precedence relationships and estimated duration times,on a time line.

(Essay)
5.0/5
(42)

Table 3.3 Table 3.3    -Using Table 3.3,what is the earliest completion time for this project? -Using Table 3.3,what is the earliest completion time for this project?

(Multiple Choice)
4.9/5
(31)

What characteristics should project manager possess?

(Essay)
4.8/5
(29)

Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks). Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks).    -Using Table 3.12,which of the following activities has the largest amount of slack? -Using Table 3.12,which of the following activities has the largest amount of slack?

(Multiple Choice)
4.7/5
(36)

Table 3.3 Table 3.3    -Using Table 3.3,what is the largest amount of slack that any activity in the project has? -Using Table 3.3,what is the largest amount of slack that any activity in the project has?

(Multiple Choice)
4.8/5
(46)

Table 3.4 Table 3.4    -Using Table 3.4,the expected time to complete the whole project is -Using Table 3.4,the expected time to complete the whole project is

(Multiple Choice)
4.9/5
(41)

The duration of an entire project is determined by the earliest finish time (EF)for the last activity on the critical path.

(True/False)
4.8/5
(35)

Assuming a beta distribution is being used,if the most optimistic time for an activity decreases by 12 days,what will happen to the expected time for that activity?

(Multiple Choice)
4.8/5
(32)
Showing 121 - 140 of 152
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)