Exam 8: Managing Projects
Exam 1: Creating Customer Value Through Operations92 Questions
Exam 2: Supply Chain Management100 Questions
Exam 3: Process Configuration114 Questions
Exam 4: Capacity101 Questions
Exam 5: Inventory Management152 Questions
Exam 6: Quality and Process Improvement197 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects152 Questions
Exam 9: Location and Layout197 Questions
Exam 10: Managing Demand and Forecasting139 Questions
Exam 11: Operations Planning and Scheduling123 Questions
Exam 12: Resource Planning151 Questions
Exam 13: Waiting Lines93 Questions
Exam 14: Decision Making73 Questions
Exam 15: Financial Analysis41 Questions
Exam 16: Work Measurement97 Questions
Exam 17: Learning Curve Analysis44 Questions
Exam 18: Computer-Integrated Manufacturing53 Questions
Exam 19: Acceptance Sampling Plans71 Questions
Exam 20: Simulation36 Questions
Exam 21: Special Inventory Models32 Questions
Exam 22: Linear Programming47 Questions
Select questions type
Which of the following is NOT one of the five steps involved in planning projects?
(Multiple Choice)
4.9/5
(33)
Table 3.11
You are responsible for managing a project with the
following activities (times are given in days).
-Using,Table 3.11,which of the following activities has the largest amount of slack?

(Multiple Choice)
4.8/5
(43)
________ is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
(Essay)
4.8/5
(44)
Which one of the following conditions violates the assumptions of PERT/CPM networks?
(Multiple Choice)
4.7/5
(39)
________ is an attempt to reduce the peaks and valleys in resource needs by shifting the schedules of conflicting activities within their earliest and latest start dates.
(Essay)
4.9/5
(42)
A Gantt chart is a project schedule that superimposes project activities on a time line.
(True/False)
4.9/5
(38)
When using the beta distribution for estimating activity times,
(Multiple Choice)
4.8/5
(35)
To calculate the probability of completing a project by a certain date,
(Multiple Choice)
4.8/5
(39)
Table 3.2
Time (days)
-Using Table 3.2,what is the earliest expected time of completion of the whole project?

(Multiple Choice)
4.7/5
(31)
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks).
-Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.

(Multiple Choice)
4.9/5
(32)
A(n)________ chart is a project schedule that superimposes project activities,with their precedence relationships and estimated duration times,on a time line.
(Essay)
5.0/5
(42)
Table 3.3
-Using Table 3.3,what is the earliest completion time for this project?

(Multiple Choice)
4.9/5
(31)
Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 3.12,which of the following activities has the largest amount of slack?

(Multiple Choice)
4.7/5
(36)
Table 3.3
-Using Table 3.3,what is the largest amount of slack that any activity in the project has?

(Multiple Choice)
4.8/5
(46)
Table 3.4
-Using Table 3.4,the expected time to complete the whole project is

(Multiple Choice)
4.9/5
(41)
The duration of an entire project is determined by the earliest finish time (EF)for the last activity on the critical path.
(True/False)
4.8/5
(35)
Assuming a beta distribution is being used,if the most optimistic time for an activity decreases by 12 days,what will happen to the expected time for that activity?
(Multiple Choice)
4.8/5
(32)