In controlling projects,the term close out refers to the decision to terminate a project because the actual time required to complete the project was going to exceed the completion date established in the original project plan.

(True/False)
4.8/5
(41)

Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks). Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks).    -Using Table 3.10,if the expected time for activity B is changed to 18 weeks,by how many weeks will the project's expected completion time increase? -Using Table 3.10,if the expected time for activity B is changed to 18 weeks,by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.9/5
(36)

Which one of the following situations is more appropriate for the application of project management?

(Multiple Choice)
4.9/5
(42)

A precedence relationship specifies that one activity cannot start until a preceding activity has been completed.

(True/False)
4.8/5
(44)

The ________ is the longest estimated time required to perform an activity.

(Essay)
4.8/5
(32)

Projects often cut across organizational lines.

(True/False)
4.9/5
(42)

Projects have a life cycle that consists of four parts.

(True/False)
4.8/5
(38)

To obtain the latest start and latest finish time,we must work forward through the network.

(True/False)
4.7/5
(38)

The ________ is the sequence of activities between a project's start and finish that takes the longest time to complete.

(Essay)
4.9/5
(27)

Activity slack refers to how much time an activity's completion time must be reduced by in order to shorten the critical path.

(True/False)
4.8/5
(42)

Among all the paths of activities in a project's network diagram,the critical path is the path with the most activity slack.

(True/False)
4.8/5
(36)

Table 3.9 All activity times for the project are in weeks. Table 3.9 All activity times for the project are in weeks.    -Using Table 3.9,what is the critical path of this project? -Using Table 3.9,what is the critical path of this project?

(Multiple Choice)
5.0/5
(43)

Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks). Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks).    -Using Table 3.12,if the expected time for activity D is increased to 6 weeks,by how many weeks will the project's expected completion time increase? -Using Table 3.12,if the expected time for activity D is increased to 6 weeks,by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.9/5
(35)

The activities along the critical path determine the completion time for the project.

(True/False)
4.9/5
(41)

A(n)________ is an interrelated set of activities that have a definite starting and ending point and that result in a unique outcome for a specific allocation of resources.

(Essay)
4.9/5
(44)

All activities on the critical path must be crashed,or expedited,in order to reduce the overall project completion time.

(True/False)
4.9/5
(46)

A project has three paths.A-B-C has a length of 25 days.A-D-C has a length of 15 days.Finally,A-E-C has a length of 20 days.Which one of the following statements is TRUE?

(Multiple Choice)
4.9/5
(37)

Crashing,or expediting,any activity within a project will reduce the overall project completion time.

(True/False)
4.9/5
(44)

Total slack for an activity is calculated by adding up the time required to complete all activities that follow the activity in the project.

(True/False)
4.8/5
(43)

Risk is a measure of the probability and consequences of not reaching a defined project goal.

(True/False)
4.8/5
(37)