Exam 8: Managing Projects
Exam 1: Creating Customer Value Through Operations92 Questions
Exam 2: Supply Chain Management100 Questions
Exam 3: Process Configuration114 Questions
Exam 4: Capacity101 Questions
Exam 5: Inventory Management152 Questions
Exam 6: Quality and Process Improvement197 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects152 Questions
Exam 9: Location and Layout197 Questions
Exam 10: Managing Demand and Forecasting139 Questions
Exam 11: Operations Planning and Scheduling123 Questions
Exam 12: Resource Planning151 Questions
Exam 13: Waiting Lines93 Questions
Exam 14: Decision Making73 Questions
Exam 15: Financial Analysis41 Questions
Exam 16: Work Measurement97 Questions
Exam 17: Learning Curve Analysis44 Questions
Exam 18: Computer-Integrated Manufacturing53 Questions
Exam 19: Acceptance Sampling Plans71 Questions
Exam 20: Simulation36 Questions
Exam 21: Special Inventory Models32 Questions
Exam 22: Linear Programming47 Questions
Select questions type
Table 3.5
-Using Table 3.5,what is the earliest completion time of this project?

(Multiple Choice)
5.0/5
(42)
________ is the shortest time in which an activity can be completed,if all goes exceptionally well.
(Essay)
4.9/5
(24)
Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 3.13,if the expected time for activity E is decreased to 8 weeks,what is the new expected completion time for the project?

(Multiple Choice)
4.8/5
(40)
Table 3.9
All activity times for the project are in weeks.
-Using Table 3.9,what is the probability that the project will be completed in 24 weeks or less? You will need to refer to a standard normal table to answer the question.

(Multiple Choice)
4.8/5
(33)
Table 3.9
All activity times for the project are in weeks.
-Using Table 3.9,if the expected time for activity E is changed to 9 weeks,by how many weeks will the projects expected completion time increase?

(Multiple Choice)
4.8/5
(31)
________ is the maximum length of time that an activity can be delayed without delaying the entire project.
(Essay)
4.9/5
(34)
Which one of the following statements about network diagrams is TRUE?
(Multiple Choice)
4.8/5
(41)
Table 3.1
Time (weeks)
-Using Table 3.1,what is the earliest expected time of completion of the whole project?

(Multiple Choice)
4.9/5
(27)
Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 3.13,what is the critical path and the expected completion time for this project?

(Multiple Choice)
5.0/5
(36)
Many small incremental changes to project objectives,which in total significantly expand the scope are referred to as ________.
(Essay)
4.8/5
(36)
Table 3.8
-Using Table 3.8,what is the slack for activity A?

(Multiple Choice)
4.8/5
(36)
The correct sequence of the four major phases in projects life cycle is;organization,planning,execution and closeout.
(True/False)
4.8/5
(44)
A(n)________ depicts the relationships between activities,which consists of nodes (circles)and arcs (arrows).
(Essay)
4.9/5
(40)
Table 3.2
Time (days)
-Using Table 3.2,which activity is on the critical path?

(Multiple Choice)
4.8/5
(42)
In planning projects,the acronym WBS stands for "work behind schedule."
(True/False)
4.8/5
(36)
Assuming a beta distribution is being used,if the most pessimistic time for an activity increases by 6 weeks,what will happen to the expected time for that activity?
(Multiple Choice)
4.8/5
(37)
If one activity along the critical path is delayed,the entire project will be delayed.
(True/False)
4.8/5
(45)