The network diagram is a planning method that is designed to depict the relationships between activities.

(True/False)
4.9/5
(45)

Which of the following statements concerning the critical path in project network is FALSE?

(Multiple Choice)
4.9/5
(37)

The critical path method (CPM)is a network planning method initially developed as a means to schedule maintenance shutdowns at chemical plants.

(True/False)
4.9/5
(30)

Table 3.5 Table 3.5    -Using Table 3.5,what is the critical path of this project? -Using Table 3.5,what is the critical path of this project?

(Multiple Choice)
4.8/5
(35)

Activity slack is the maximum length of time that an activity can be delayed without delaying the entire project.

(True/False)
4.7/5
(39)

In monitoring a project,negative slack indicates how much an activity has been pushed beyond its planned latest start dates.

(True/False)
4.8/5
(28)

What options do project managers have to alleviate resource problems? Briefly describe each method.

(Essay)
4.7/5
(33)

What are the five steps involved in planning a project?

(Essay)
4.8/5
(28)

One of duties of the project manager is to make sure that issues that have been raised during the project actually get resolved in a timely fashion.

(True/False)
4.7/5
(33)

Table 3.1 Time (weeks) Table 3.1 Time (weeks)    -Using Table 3.1,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase? -Using Table 3.1,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?

(Multiple Choice)
4.8/5
(37)

The probability that a project will be completed by its earliest expected completion date is

(Multiple Choice)
4.7/5
(27)

For controlling projects,the Cost Performance Index (CPI)measures the ratio of the budgeted cost of the work completed to date divided by the actual cost for that same work.

(True/False)
4.8/5
(34)