Exam 16: Resource Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Explain why,in a dependent demand environment,MRP does a better job of estimating the need to replenish inventory items than does the reorder point system.

Free
(Essay)
4.7/5
(37)
Correct Answer:
Verified

MRP works better for dependent-demand environments because statistical forecasting for components with lumpy demand results in large forecast errors.It also provides managers with information useful for planning capacities and estimating financial requirements,and it automatically updates the demand and inventory-replenishment schedules of components when the production schedule of parent items changes.

Operations produces a number of items in one production period.Those items that are not produced for a specific customer order are ________.

Free
(Essay)
5.0/5
(40)
Correct Answer:
Verified

available to promise

Table 16.1 Table 16.1   -Use the information in partially completed Table 16.1.What is the MPS start quantity in week 4? -Use the information in partially completed Table 16.1.What is the MPS start quantity in week 4?

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
Verified

A

Complete the following MPS Record Complete the following MPS Record

(Essay)
4.9/5
(34)

Management wishes to use a POQ lot-sizing rule for an item that experiences an average demand of 30 units per week.If the desired average lot size is 120 units,what should P be?

(Multiple Choice)
4.8/5
(36)

Table 16.3 Table 16.3   -Use the following MRP record to answer the question.   What are the quantity and the week of the first planned order release? -Use the following MRP record to answer the question. Table 16.3   -Use the following MRP record to answer the question.   What are the quantity and the week of the first planned order release? What are the quantity and the week of the first planned order release?

(Multiple Choice)
4.9/5
(44)

Complete the following MRP record using the FOQ rule: Complete the following MRP record using the FOQ rule:

(Essay)
4.8/5
(29)

Table 16.2 Table 16.2   -Use the information in partially completed Table 16.2.What is the available-to-promise (ATP)inventory in week 6? -Use the information in partially completed Table 16.2.What is the available-to-promise (ATP)inventory in week 6?

(Multiple Choice)
4.8/5
(33)

Which of the following statements about service resource planning is TRUE?

(Multiple Choice)
4.7/5
(37)

Figure 16.8 Figure 16.8     Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. -Use Figure 16.8 to answer this question.How many additional units of F are needed to produce twelve end items? Figure 16.8     Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. -Use Figure 16.8 to answer this question.How many additional units of F are needed to produce twelve end items? Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. -Use Figure 16.8 to answer this question.How many additional units of F are needed to produce twelve end items?

(Multiple Choice)
4.8/5
(32)

Table 16.4 Consider the following MPS,BOM,and inventory data.Blank MRP records are provided at the end of this exam. Master Production Schedule: The following table shows the MPS start quantities. Table 16.4 Consider the following MPS,BOM,and inventory data.Blank MRP records are provided at the end of this exam. Master Production Schedule: The following table shows the MPS start quantities.   Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data   -Use the information in Table 16.4.Which one of the following statements about item C is BEST? Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data Table 16.4 Consider the following MPS,BOM,and inventory data.Blank MRP records are provided at the end of this exam. Master Production Schedule: The following table shows the MPS start quantities.   Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data   -Use the information in Table 16.4.Which one of the following statements about item C is BEST? -Use the information in Table 16.4.Which one of the following statements about item C is BEST?

(Multiple Choice)
4.8/5
(29)

Table 16.7 Viola Products produces one item with the following bill of materials Table 16.7 Viola Products produces one item with the following bill of materials   A recent check of their inventory reveals the following quantities on hand.    Currently no scheduled receipts exist for any of the dependent demand items. -Use Table 16.7 to answer this question.How many additional units of J are needed to produce seven end items? A recent check of their inventory reveals the following quantities on hand. Table 16.7 Viola Products produces one item with the following bill of materials   A recent check of their inventory reveals the following quantities on hand.    Currently no scheduled receipts exist for any of the dependent demand items. -Use Table 16.7 to answer this question.How many additional units of J are needed to produce seven end items? Currently no scheduled receipts exist for any of the dependent demand items. -Use Table 16.7 to answer this question.How many additional units of J are needed to produce seven end items?

(Multiple Choice)
4.9/5
(36)

Table 16.6 Table 16.6   -Use the information from Table 16.6.If an FOQ of 80 units is used,how many planned order releases are there for item XYZ? -Use the information from Table 16.6.If an FOQ of 80 units is used,how many planned order releases are there for item XYZ?

(Multiple Choice)
4.9/5
(31)

Which one of the following is an input to the MRP system?

(Multiple Choice)
4.8/5
(36)

Complete the following MRP record using the POQ rule. Complete the following MRP record using the POQ rule.

(Essay)
4.8/5
(34)

Complete the following MRP record using the L4L rule: Complete the following MRP record using the L4L rule:

(Essay)
4.9/5
(39)

Explain the difference between independent and dependent demand and illustrate your explanation with an example.

(Essay)
4.8/5
(39)

Which one of the following is a feature of MRP II,but not available in basic MRP systems?

(Multiple Choice)
4.9/5
(36)

Which of the following statements concerning MRP is TRUE?

(Multiple Choice)
4.8/5
(39)

Case Study 16.1 Sunshine Manufacturing produces three products: X,Y,Z.The production of these end items is controlled by an MRP system.Each end item X is assembled with two components of A and one component of B.Each end item of Y is assembled with two components of C and one component of A.End item Z is assembled from one unit of D and one unit of C;D is manufactured from one unit of A;and C is manufactured from one unit of B. -Use the information in Case Study 16.1.Which of the following sequences is an acceptable way to process the inventory records for components A,B,C,and D?

(Multiple Choice)
5.0/5
(34)