Exam 24: Learning Curve Analysis

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

When the learning curve has a pronounced curve,the production phase could be characterized as the ________.

(Essay)
4.8/5
(31)

A task that obeys learning effects will,in general,have a positive result to the equation tn+1tn,where tn is the completion time of the nth unit.

(True/False)
4.8/5
(41)

The first unit took fifteen days to finish and the second unit was finished a mere 13.5 days later.How long will it take to finish the eighth unit?

(Multiple Choice)
4.8/5
(30)

I.3 Using Learning Curves Case I.1 The production schedule for a new product follows. I.3 Using Learning Curves Case I.1 The production schedule for a new product follows.    The first unit took 100 hours to complete,and the rate of learning is 80 percent.Each employee works 40 hours per month.Refer to the copy of Table I.1 appended to this exam. -Using the information in Case I.1,how much time will it take to produce the units in month 1? The first unit took 100 hours to complete,and the rate of learning is 80 percent.Each employee works 40 hours per month.Refer to the copy of Table I.1 appended to this exam. -Using the information in Case I.1,how much time will it take to produce the units in month 1?

(Multiple Choice)
4.8/5
(38)

The estimated time to produce the first unit is 100 hours.If a 90 percent learning rate is applicable,what is the estimated time of producing the first ten units? Refer to the copy of Table I.1 appended to this exam.

(Essay)
4.7/5
(42)

Which one of the following statements is TRUE about the relationship between learning curves and competitive strategy?

(Multiple Choice)
4.8/5
(32)

It took 100 hours to produce the first unit and the learning rate is 80 percent.How much time will it take to produce units 16 through 20? Refer to the copy of Table I.1 appended to this exam.

(Multiple Choice)
4.9/5
(43)

The mathematical model that is used to generate a learning curve is ________.

(Essay)
4.8/5
(35)

Which one of the following is an assumption of learning curves?

(Multiple Choice)
4.8/5
(39)

It took 100 hours to produce the first unit and 95 hours to produce the second unit.How many hours are required to produce the eighth unit? [Note: a calculator is required to answer this question.]

(Multiple Choice)
4.8/5
(38)

In Troix City,the learning rate is based on a tripling of output instead of the traditional doubling.The first unit of a long production run was produced in 25 hours.The process has an estimated learning rate of 80 percent.How long will the 9th unit take to produce?

(Multiple Choice)
4.8/5
(43)