Exam 12: Project Management
Exam 1: Introduction to Quantitative Analysis63 Questions
Exam 2: Probability Concepts and Applications145 Questions
Exam 3: Decision Analysis119 Questions
Exam 4: Regression Models120 Questions
Exam 5: Forecasting101 Questions
Exam 6: Inventory Control Models113 Questions
Exam 7: Linear Programming Models: Graphical and Computer Methods100 Questions
Exam 8: Linear Programming Applications96 Questions
Exam 9: Transportation and Assignment Models80 Questions
Exam 10: Integer Programming, Goal Programming, and Nonlinear Programming88 Questions
Exam 11: Network Models86 Questions
Exam 12: Project Management123 Questions
Exam 13: Waiting Lines and Queuing Theory Models133 Questions
Exam 14: Simulation Modeling68 Questions
Exam 15: Markov Analysis78 Questions
Exam 16: Statistical Quality Control87 Questions
Select questions type
One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.
Free
(True/False)
4.7/5
(32)
Correct Answer:
True
Table 12-5
-How long could Table 12-5's activity E be delayed without delaying the completion of the project?

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
C
Table 12-6
-Which activities are part of Table 12-6's critical path?

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
D
Consider the project with the following estimates for activity times and precedence relationships:
(a) What is the expected duration of the project?
(b) What is the project variance?
(c) If the deadline of the project is 25 days, what is the probability of finishing the project on time?

(Essay)
4.9/5
(40)
PERT often assumes that time estimates follow which of the following probability distributions?
(Multiple Choice)
4.7/5
(34)
Table 12-5
-How long could Table 12-5's activity F be delayed without delaying the project?

(Multiple Choice)
4.8/5
(39)
One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.
(True/False)
4.9/5
(35)
Slack is the time an activity can be delayed without impacting the completion time of the project.
(True/False)
4.9/5
(35)
The project described by:
has a critical path of length of ________.

(Multiple Choice)
4.7/5
(29)
In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.
(True/False)
4.9/5
(32)
Reducing the overall activity time is based on which of the following steps?
(Multiple Choice)
4.8/5
(35)
Given the variability of the activity completion times, the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.
(True/False)
4.8/5
(40)
Figure 12-1
-Given the network in Figure 12-1, the time to complete those activities on the critical path is expected to be ________.

(Multiple Choice)
4.9/5
(29)
The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.
(True/False)
4.9/5
(36)
Showing 1 - 20 of 123
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)