Exam 12: Project Management
Exam 1: Introduction to Quantitative Analysis63 Questions
Exam 2: Probability Concepts and Applications145 Questions
Exam 3: Decision Analysis119 Questions
Exam 4: Regression Models120 Questions
Exam 5: Forecasting101 Questions
Exam 6: Inventory Control Models113 Questions
Exam 7: Linear Programming Models: Graphical and Computer Methods100 Questions
Exam 8: Linear Programming Applications96 Questions
Exam 9: Transportation and Assignment Models80 Questions
Exam 10: Integer Programming, Goal Programming, and Nonlinear Programming88 Questions
Exam 11: Network Models86 Questions
Exam 12: Project Management123 Questions
Exam 13: Waiting Lines and Queuing Theory Models133 Questions
Exam 14: Simulation Modeling68 Questions
Exam 15: Markov Analysis78 Questions
Exam 16: Statistical Quality Control87 Questions
Select questions type
Given (Time in weeks):
Determine:
(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.


(Essay)
4.9/5
(48)
Table 12-4
The following represents a project with known activity times. All times are in weeks.
-Using the data in Table 12-4, determine the latest time activity A can be finished and not delay any activity?

(Multiple Choice)
4.7/5
(30)
Table 12-2
The following represents a project with four activities. All times are in weeks.
-According to the data in Table 12-2, what is the critical path?

(Multiple Choice)
4.9/5
(45)
Table 12-1
The following represents a project with know activity times. All times are in weeks.
-According to Table 12-1, compute the slack time for activity D.

(Multiple Choice)
4.7/5
(42)
Before drawing a PERT or CPM network, we must identify all activities and their predecessors.
(True/False)
4.9/5
(31)
A small software development project has five major activities. The times are estimated and provided in the table below.
(a) What is the expected completion time for this project?
(b) What variance would be used in finding probabilities of finishing by a certain time?

(Essay)
4.8/5
(37)
Table 12-3
-According to Table 12-3, there are five activities in a PERT project. If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?

(Multiple Choice)
4.7/5
(38)
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)
(Multiple Choice)
4.9/5
(38)
Consider the following project schedule:
(a) Which activities are critical?
(b) Which activity has the most slack?

(Essay)
4.8/5
(31)
Figure 12-1
-Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four days. What changes will take place?

(Multiple Choice)
4.8/5
(40)
An alternative approach to project crashing is to use which of the following techniques?
(Multiple Choice)
4.9/5
(38)
Both PERT and CPM networks show activities and activity sequences.
(True/False)
4.8/5
(38)
The work breakdown structure involves identifying the ________ for each activity.
(Multiple Choice)
4.8/5
(40)
Table 12-3
-According to Table 12-3, there are five activities in a PERT project. Which activities are on the critical path?

(Multiple Choice)
4.8/5
(41)
Your company is considering submitting a bid on a major project. You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies. You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time. What due date should be set?
(Multiple Choice)
4.9/5
(40)
A small software development project has four major activities. The times are estimated and provided in the table below.
(a) What is the expected completion time for this project?
(b) What variance would be used in finding probabilities of finishing by a certain time?

(Essay)
4.9/5
(41)
Showing 21 - 40 of 123
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)